Seismic Design of Cast-in-Place Concrete Special Structural Walls and Coupling Beams: A Guide for Practicing Engineers
32
The rst splice of vertical reinforcement typically occurs
immediately above the foundation, where wall longitudinal
reinforcement laps with dowel bars. These dowels provide
the critical mechanism of transferring tension and shear
forces from the structural wall to the foundation. All vertical
reinforcement must be extended into the foundation a depth
sufcient to be fully developed for tension. For constructability
purposes, it is recommended that dowels with 90° hooks extend
to the bottom of the foundation where they can be tied rmly
the foundation bottom reinforcement.
For structural walls with two curtains of reinforcement, it
is preferred for the vertical reinforcement to be inside the
horizontal reinforcement. This arrangement improves splice
strength and buckling restraint for the verticals.
Horizontal reinforcement is always treated as “top-cast”
reinforcement, requiring
ψ
t
= 1.3 for all development and
lap splice length calculations. Splice locations might not be
nalized until the contractor has determined the breakdown of
pre-tied segments and the overall erection sequence including
formwork operability. For structural walls with pre-tied
segments, the horizontal reinforcement has the additional
function of tying the pieces together in the nal arrangement
(Figure 7-1).
7.5 Miscellaneous Detailing Issues
As signicant obstructing elements, structural walls must be
closely coordinated with mechanical, electrical, and plumbing
designs to enable the routing and distribution of these systems.
Although it is preferable to spatially separate structural walls
from the nonstructural components introduced by other
trades, it is often necessary to provide blockouts and sleeves
to allow for minor penetration of the structural walls. It is
recommended to identify early those areas that are not available
for penetrations, typically boundary elements, coupling beams,
and the development zone of coupling beams in wall ends.
Where penetrations occur, it is important to provide trim
reinforcement around all edges. The exact layout and size of
trim reinforcement should be selected to provide a complete
load path for all local forces and to inhibit cracking of the walls
along the sides of the penetrations.
The transfer of diaphragm forces between slabs and structural
walls is ideally detailed in a distributed manner. Where this
cannot be accomplished, due to large slab openings or very
large transfer forces, horizontal collector elements must be
created. At the wall-to-slab interface, this generally takes
the form of large quantities of longitudinal reinforcement.
Collector forces must be fully resolved into the wall end,
requiring embedment in excess of a typical development
length when the wall horizontal reinforcement is insufcient
to provide a complete splice.
When steel elements are framed to structural walls, the
connection detail typically takes the form of an embedded
steel plate with deformed bars or headed studs welded to that
plate and developed into the backing structural wall. This is a
frequent occurrence for structural walls enclosing and forming
an elevator core. Steel members will be required to separate
multi-bank elevators, and to support elevator and counterweight
rails. These members must be attached to the structural walls
in very precise locations. To allow for tolerance in placement
of the embedded steel connection plates, it is recommended
to oversize the plates to allow for misplacement up to 3 inches
without compromising the integrity of the connection.
7.6 Concrete Placement
Similar to column construction, the placement of structural
wall concrete in high-aspect-ratio (height/width) forms
inevitably includes the issues of concrete drop height, blind
vibration, practical lift heights, and selection of a mixture
with appropriate owability. These issues need to be clearly
discussed and coordinated with the contractor to ensure that the
nal product is fully consolidated, monolithic, and isotropic.
The intersection of slabs and structural walls is a region in
which the placement sequence and resulting concrete strength
needs to be closely considered. For multi-story construction,
structural walls are typically cast to the underside of the slab
above. The slab is cast over the top of the wall, and the wall
construction resumes above. This results in a plane of slab
concrete placed through the structural wall. The standard
remedy is to place higher strength concrete in the slab over
the top of the structural wall, extending two feet beyond the
face of the wall. This method, typically called puddling, must
be carefully scheduled with the slab pour to ensure that the
high strength concrete is well integrated with the remainder
of the slab.
The slip-form method of constructing structural walls
eliminates this weakened plane at the structural wall-to-slab
intersection. In this and other similar wall forming techniques,
the structural wall is cast continuously through the depth of
the slab, construction joints notwithstanding. Although this
method avoids the potential for insufcient concrete strength
in the structural wall, the slab-to-wall connection must be
detailed to accommodate all force transfers. This critical
location must transfer vertical shear from gravity forces in the
slab and in-plane horizontal shear from diaphragm forces, and
it must maintain integrity during drift-induced rotation of the
slab-to-wall connection. Shear keys can help transfer shear
forces at this otherwise smooth interface. Reinforcement
details must be selected with due consideration of anticipated
local deformations during earthquake shaking.