Answer: If you are using in excess of 100 pounds of CO2 the Code does obligate a number of additional
requirements. The IFC requires a number of items including detection systems, ventilation, signage, and
many other considerations. In instances where an applicant desires to use this process a professional
engineer must design the CO2 system, safety features, and mechanical systems with plans
demonstrating compliance with the codes submitted with the permit. The submittal must clearly state,
"The system was designed in accordance with the 2018 IFC with amendments from the OUBCC."
Question: Can we install exposed visqueen or plastic/polyethylene sheathing materials in a building?
Answer: Typically no. Building materials must pass flame and smoke spread ratings. To be used in most
areas a flame spread index 76-200 and a smoke spread of 0-450 are required. If it is a greenhouse
permitted as a U occupancy, materials are not required to comply with this standard.
Question: How many and where will I be required to install portable fire extinguishers in my medical
marijuana related business?
Answer: The building must meet 2018 NFPA 10 Standard for portable fire extinguishers; you can find a
read only version HERE.
Question: What considerations have to be made for fire department access to the building?
Answer: The fire access road must meet 2018 IFC Appendix D. You can find a read only version HERE.
Question: I received a building permit for a medical marijuana business. What inspections should I
expect?
Answer: A new building will likely have the following inspections: foundation, slab, plumbing ground,
plumbing sewer service, plumbing water service, exterior sheathing, electrical rough in and permanent
service, plumbing top out, framing, wall insulation, mechanical duct overhead, Plumbing Final,
Mechanical Final, Electrical Final, Building Final, Fire Marshal Final, Planning Final, Public Works Final.
An existing building being converted is likely to need all the following inspections: electrical rough in and
permanent service, plumbing top out, framing, wall insulation, mechanical duct overhead, Plumbing
Final, Mechanical Final, Electrical Final, Building Final, Fire Marshall Final, Planning Final, Public Works
Final.
Question: How do I schedule inspections?
Answer: You may request inspections online from your portal account HERE.
IF you are having troubles,
you can call 405-366-5346.