Change the Days per month to 30.
Press the OK button, when the above changes have been completed.
Notes:
If you have resources in the Resource Sheet view of your project, you should also
change their Base Calendar value to the 24 Hours calendar.
If you have entered tasks with durations prior to making the changes above,
you may need to re-enter the durations to their correct values for each task.
Steps for 2007 Users
From the menu, select Project > Project Information.
Press the Calendar drop-down list and select the 24 Hours calendar and then press
the OK button.
From the menu, select Format > Timescale.
Select the Non-Working time tab, and press the Calendar drop-down list and
select the 24 Hours calendar. Next press the OK button.
From the menu, select Tools > Options > Calendar.
Make the following changes:
Change the Hours per week value to 168.
Change the Hours per day value to 24.
Change the Default start time value and the Default end time value to 12:00 AM.
Change the Days per month to 30.
Press the OK button, when the above changes have been completed.
Notes:
If you have resources in the Resource Sheet view of your project, you should also
change their Base
Calendar value to the 24 Hours calendar.