e-Builder Schedule Module
Page xiv
l
Toggle: Click to show or hide the baseline.
Columns Available in all Schedules
l
Task Name: Displays the name of the task
l
Duration: Task duration in days (Note: for parent tasks, the units automatically changes to
Weeks for Duration >20 days, and changes to Months, for Durations >26 Weeks)
l
Predecessors: The tasks that precedes the task (Options are FS, SS, FF, SF)
l
Successors: The tasks that succeeds the task (Options are FS, SS, FF, SF)
l
Start: The planned start date for a task.
l
Finish: The planned finish date for a task.
l
% Complete: The manually updated progress, as a percentage of duration, on a task (may also
be automatically calculated as of the current date, if the schedule setting is enabled to "Auto-
matically calculate the % complete").
l
Early Start: The earliest date that a task can start based on any dependencies and constraints.
l
Early Finish: The earliest date that a task can finish based on the Early Start date plus Duration,
as well as any dependencies and constraints.
l
Late Start: The latest date that a task can start in order to meet any successor Milestones (such
as a Project Finish No Later Than Constraint on a Project Finish milestone)
l
Late Finish: The latest date that a task must finish in order to meet any successor milestones
(such as a Finish No Later Than Constraint on a Project Finish milestone).
l
Baseline Duration: The duration in days on each selected task at the moment that the baseline
was last set.
l
Baseline Start Date: The start date on each selected task at the moment that the baseline was
last set.
l
Baseline Finish Date: The finish date on each selected task at the moment that the baseline
was last set.
l
Baseline % Complete: The manually updated progress, as a percentage of duration, on each
selected task at the moment that the baseline was last set.
l
Calendar: Select from the available project calendars.
l
Constraint: Select the type of constraint to be applied to a task (Options are: None, As late as
possible, As soon as possible, Finish no earlier than, Finish no later than, Must finish on, Must
start on, Start no earlier than, Start no later than)
l
Constraint Date: Select the date that is desired to coincide with the constraint type. To remove a
constraint, you must first change the Constraint Type to "None".
l
Critical: Indicates that a task is on the critical path (longest path) for the project schedule.
l
Start Variance: Start Variance = Start - Baseline Start Date
Values are either: N days Late, N d Early, or 0d (Example: 2d Early, 3d Late)
l
Finish Variance: Finish Variance = Finish - Baseline Finish Date