DCMA Manual 2501-11
International Requests for
Contract Administration Services
==========================================================
Office of Primary
Responsibility Contract Maintenance Capability
Effective: March 4, 2019
Change 1 Effective: September 25, 2019
Releasability: Cleared for public release
Implements: DCMA-INST 2501, “Contract Maintenance,” August 14, 2017
Incorporates and cancels: DCMA-INST 313, “International Requests for Contract
Administration Services,” November 23, 2013, as amended
Internal Control: Process flow and key controls are located on the Resource Page
Labor Codes: Located on the Resource Page
Resource Page Link: https://360.dcma.mil/sites/policy/CM/SitePages/2501-11r.aspx
Approved by: David H. Lewis, VADM, USN, Director
__________________________________________________________________
Purpose: This issuance, is in accordance with the authority in DoD Directive 5105.64:
Implements policy established in DCMA Instruction 2501
Assigns responsibility, and defines procedures for DCMA Functional Specialist both
continental U.S. and at foreign locations, when requesting a foreign government, as the
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
2
Host Nation to perform government quality assurance, financial services, or other
contract administration services on behalf to the United States within their country
Assigns responsibility, and defines procedures when DCMA, as the Host Nation,
performs government quality assurance, financial services, or other contract
administration services on behalf of a foreign government or international organization
such as the North Atlantic Treaty Organization, within the U.S.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Table of Contents 3
TABLE OF CONTENTS
SECTION 1: GENERAL ISSUANCE INFORMATION ..........................................................6
1.1. Applicability .......................................................................................................................6
1.2. Policy .................................................................................................................................6
SECTION 2: RESPONSIBILITIES ............................................................................................8
2.1. Commander, DCMA International Command. ..................................................................8
2.2. Functional Director, DCMA International .........................................................................8
2.3. DoD Central Control Point International Contract Services Manager ...............................8
2.4. Commander, DCMA International Contract Management Office .....................................9
2.5. Host Nation Coordinator, DCMA International Contract Management Office ..................9
2.6. DCMA International Contract Management Office First Level Supervisor .......................9
2.7. DCMA International Contract Management Office Functional Specialist ....................... 10
2.8. Commander, DCMA CONUS Contract Management Office .......................................... 10
2.9. DCMA CONUS Contract Management Office First Level Supervisor ........................... 10
2.10. DCMA CONUS Contract Management Office Functional Specialist............................ 11
SECTION 3: DELEGATION PROCEDURE DCMA CONTRACT MANAGEMENT
OFFICE TO DCMA INTERNATIONAL CONTRACT MANAGEMENT OFFICE ........... 12
3.1. Process Steps .................................................................................................................... 12
3.2. Coordination ..................................................................................................................... 13
SECTION 4: REQUEST FOR GOVERNMENT QUALITY ASSURANCE
PROCEDURE DCMA INTERNATIONAL CONTRACT MANAGEMENT OFFICE
TO A FOREIGN GOVERNMENT ............................................................................................ 14
4.1. Process Input/Output ........................................................................................................ 14
4.2. Contract Receipt and Review and Exceptions to Requesting Contract Administration ......
Services ............................................................................................................................ 14
4.3. Perform Risk Assessment and Prepare Risk Identification, Assessment and ......................
Communication Form ....................................................................................................... 15
4.4. Prepare the Surveillance Plan ........................................................................................... 18
4.5. Facility-Wide Request for Government Quality Assurance ............................................. 19
4.6. Prepare Request for Government Quality Assurance ....................................................... 20
4.7. Forward Request for Government Quality Assurance to Applicable Host Nation Focal
Point ................................................................................................................................. 22
4.8. Manage Rejected Request for Government Quality Assurance ....................................... 23
4.9. Perform Product Acceptance and Release ........................................................................ 23
4.10. Receive Government Quality Assurance Closure Report/Risk Identification Assessment
and Communication form and Maintain Records ........................................................... 24
4.11. Close Contract Delegation .............................................................................................. 25
SECTION 5: GOVERNMENT QUALITY ASSURANCE PERFORMANCE
FOREIGN GOVERNMENT ....................................................................................................... 26
5.1. Process Input/Output ........................................................................................................ 26
5.2. Government Quality Assurance Performance by the Host Nation Quality Assurance
Organization ..................................................................................................................... 26
5.3. Government Quality Assurance Closure Report .............................................................. 26
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Table of Contents 4
SECTION 6: REQUEST FOR FINANCIAL SERVICES - DCMA INTERNATIONAL
CONTRACT MANAGEMENT OFFICE TO A FOREIGN GOVERNMENT .................... 27
6.1. Foreign Audit Services Requests (Canada) ..................................................................... 27
6.2. Perform Requested Foreign Contractor Pricing Assistance – DCMA International
Contract Management Office (Canada) ........................................................................... 27
6.3. Perform Requested Foreign Contractor Pricing Assistance – Foreign Government
(Canada) ........................................................................................................................... 28
6.4. Foreign Contractor Pricing Requests (Other than Canada) ............................................. 29
6.5. Pre-Award Foreign Contractor Pricing-Request from DCMA Contract Management
Office, External Customer, or Contractor (Other than Canada) ....................................... 30
6.6. Perform Requested Foreign Contractor Pricing Assistance – Foreign Government (Other
than Canada) .................................................................................................................... 30
SECTION 7: REQUEST FOR GOVERNMENT QUALITY ASSURANCE
PROCEDURE TO DEPARTMENT OF DEFENSE CENTRAL CONTROL POINT ......... 32
7.1. Process Input/Output ........................................................................................................ 32
7.2. Allied Quality Assurance Publication - 2070/International Agreement/ Government
Quality Assurance Administration Procedure Requirements ........................................... 32
SECTION 8: REQUEST FOR CONTRACT ADMINISTRATION SERVICE
PROCEDURE TO DEPARTMENT OF DEFENSE CENTRAL CONTROL POINT ......... 34
8.1. Process Input/Output ........................................................................................................ 34
8.2. Determine if Labor Rates apply and enter request into the Agency system of record
for RGQAs ....................................................................................................................... 34
8.3. Acknowledge Request ...................................................................................................... 34
8.4. Transmit Request to DCMA Contract Management Office via the Agency system of
record for RGQAs ............................................................................................................ 35
8.5. Closure of Request ........................................................................................................... 35
SECTION 9: REQUEST FOR CONTRACT ADMINISTRATIVE SERVICE
PROCEDURE GOVERNMENT QUALITY ASSURANCE PERFORMANCE -
DCMA CONTRACT MANAGEMENT OFFICE .................................................................... 36
9.1. Process Input/Output ........................................................................................................ 36
9.2. Response to Government Quality Assurance Request ..................................................... 36
9.3. Government Quality Assurance Surveillance Planning .................................................... 37
9.4. Perform Government Quality Assurance Surveillance ..................................................... 38
9.5. Government Quality Assurance Closure Report .............................................................. 38
9.6. Closure of Request ........................................................................................................... 40
SECTION 10: EXPORT CONTROLS...................................................................................... 41
10.1. International Traffic in Arms Regulation/Export Administration Regulations
overview related to international requests for Contract Administration Services ........... 41
10.2. Safeguarding Controlled Unclassified Information ........................................................ 43
10.3. International Traffic in Arms Regulation -Related Request Procedure DCMA .............
Contract Management Office ......................................................................................... 43
10.4. International Traffic in Arms Regulation -Related Request Procedure DCMA
International Contract Management Office .................................................................... 44
GLOSSARY
G.1. Definitions ....................................................................................................................... 48
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Table of Contents 5
G.2. Acronyms ........................................................................................................................ 50
REFERENCES ............................................................................................................................. 52
FIGURES
Figure 1. Risk Identification Assessment and Communication Form Example ............................ 16
Figure 2. Risk Index of AQAP-2070 ............................................................................................ 17
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 1: General Issuance Information 6
SECTION 1: GENERAL ISSUANCE INFORMATION
1.1. APPLICABILITY. This Manual applies to DCMA organizations involved in the
exchange of Contract Administration Services (CAS) with a foreign government under the terms
of an International Agreement. This includes DCMA Contract Management Offices (CMOs)
within the contintental US (CONUS) delegating to DCMA International (DCMAI) CMOs
outside the US (OCONUS).
1.2. POLICY. It is DCMA policy that:
a. Supplemental to DCMA Instruction (DCMA-INST) 2501, “Contract Maintenance,
paragraph 1.2.a., DCMA Functional Specialist (FS) must not enter into discussions with FS from
foreign governments concerning the establishment of International Agreements or extending the
provisions of current International Agreements without the expressed written authorization to do
so by the Office of the Under Secretary of Defense for Acquisition and Sustainment (OUSD
A&S), pursuant to DoD Directive (DoDD) 5530.3, “International Agreements.”
b. DCMA must utilize existing International Agreements, where applicable, for the
reciprocal exchange of CAS when the performance of such services is considered necessary in
the other country or when requested by a foreign government. Once the request for CAS is
accepted by the other government’s CAS organization, DCMA FS must not provide any
additional/duplicate CAS activities, nor will they perform oversight of the CAS performed by the
Host Nation (HN). Any travel associated with OCONUS delegations must be in accordance with
DCMA travel instructions.
c. Except as identified in this Manual, the process mandated herein takes precedence over
other DCMA Manuals when requesting or performing CAS under the provisions of an existing
International Agreement. Whenever a contract cannot be delegated to the HN, DCMA FS must
perform CAS in accordance with the applicable CAS process instructions.
d. All requests for government quality assurance (GQA) made to another government by
DCMA must be initiated by DCMAI CMOs. Foreign field pricing and assist audit requests for
foreign contractors (Prime or subcontractor) may be initiated by an internal (DCMA) requestor,
an external (non-DCMA government activity) requestor, or a contractor.
e. All CAS requests made by another government to DCMA must only be received and
processed by the DoD Central Control Point (DoDCCP) in accordance with Defense Federal
Acquisition Regulation Supplement (DFARS) 242.002, “Interagency Agreements.”
f. DCMA FS must comply with North Atlantic Treaty Organization (NATO)
Standardization Agreement (STANAG) 4107, “Mutual Acceptance of Government Quality
Assurance and Usage of the Allied Quality Assurance Publications (AQAP),” AQAP 2070,
“NATO Mutual Government Quality Assurance Process,” and this Manual when asking a NATO
member nation to perform GQA and when performing GQA when requested by a NATO nation
or NATO organization.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 1: General Issuance Information 7
g. DCMA FS must comply with International Traffic in Arms Regulations (ITAR), Parts
120-130 of Title 22, Code of Federal Regulations (CFR), and Export Administration Regulations
(EAR).
h. Requests for GQA (RGQA) to other governments must be based on a risk assessment
performed by DCMA quality assurance (QA) FS.
i. CAS requests must follow the associated Annex of the International Agreement for
reciprocal financial services where applicable. The nations with whom the U.S. has entered into
an agreement for CAS can be found on the Defense Pricing and Contracting (DPC) website.
j. DCMA FS must not request a foreign government to perform any other contract
administration services except property administration, National Aeronautics and Space
Administration (NASA) delegations in Canada and other CAS addressed in this Manual.
k. It is DCMA policy to execute this Manual in a safe, efficient, and ethical manner.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 2: Responsibilities 8
SECTION 2: RESPONSIBILITIES
2.1. COMMANDER, DCMA INTERNATIONAL COMMAND. The Commander, DCMAI
will:
a. Utilize the DCMAI Functional Director to monitor efforts associated with support
requests under International Agreements or assessments of a foreign government’s QA
management system capabilities received from DPC.
(1) Inform the DCMA Executive Director of QA of reciprocal assessments so that
Agency (DCMA unless otherwise identified) support can be provided, if necessary.
(2) Inform the DCMA Director of progress being made and of any anticipated delays
related to support requests.
b. Notify the DPC, DCMA Director, and the DCMA Executive Director of QA of any
International Agreement noncompliance issues that are likely to be escalated for discussion
between DoD and their foreign government counterparts.
2.2. FUNCTIONAL DIRECTOR, DCMA INTERNATIONAL. The Functional Director
must:
a. Lead efforts associated with support requests under International Agreements or
assessments of a foreign government QA Management System as requested by the DPC.
b. Liaise with the CMO Commander and HN Coordinator on International Agreements and
policy changes.
c. Coordinate reciprocal assessments with the DCMA Executive Director of QA to
determine Agency support requirements.
d. Ensure DCMA Director is informed of all rejected delegations and the progress or delays
related to support requests.
e. Provide training to HN Coordinators on NATO STANAG 4107, AQAP-2070, ITAR/EAR
and requirements associated with the flow down of requirements to subcontractors.
f. Establish and maintain performance metrics for delegations to HNs and provide a monthly
status to the DCMAI Commander.
2.3. DOD CENTRAL CONTROL POINT INTERNATIONAL CONTRACT SERVICES
MANAGER. The DoDCCP International Contract Services Manager must:
a. Manage RGQAs and requests for other services using the DCMA Agency system of
record for RGQAs.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 2: Responsibilities 9
b. Establish Agency system of record for RGQAs delegations, track required process
activities, and coordinate with DCMA CMOs to ensure timely acceptance and completion of all
requests from other governments.
c. Escalate potential noncompliance of the provisions of International Agreements or NATO
processes by either DoD FS or foreign government FS to the DCMA Director, DCMA Executive
Director of QA, and the Commander, DCMAI. The DoDCCP will make the appropriate DCMA
CMO Commander and DCMAI Functional Director aware of the situation and circumstances.
2.4. COMMANDER, DCMA INTERNATIONAL CONTRACT MANAGEMENT
OFFICE. DCMAI CMO Commanders must:
a. Escalate to the DCMAI Commander any issues dealing with noncompliance of the
provisions of International Agreements by either DoD or foreign government FS indicating
whether such noncompliance appear likely to be escalated within DoD or the HN government.
b. Ensure a process is in place to periodically review and report delegation decisions by
assigned FS.
2.5. HOST NATION COORDINATOR, DCMA INTERNATIONAL CONTRACT
MANAGEMENT OFFICE. The HN Coordinator must:
a. Support the DCMAI CMO Commander by providing training and follow-on guidance for
NATO STANAG 4107, AQAP-2070 and the requirements of the applicable International
Agreements and any established GQA administrative procedures.
b. Support the DCMAI CMO Commander by providing training and follow-on guidance in
identifying contractual requirements invoking ITAR/EAR restrictions and associated contractual
flow down of requirements to subcontractors.
c. Support the DCMAI CMO Commander in ensuring assigned FS comply with this Manual
when work is performed in any geographical location falling under the purview of an
International Agreement for the exchange of GQA or financial services. Also, ensure assigned
FS do not provide additional/duplicate CAS nor perform oversight of the GQA surveillance
performed by the HN.
d. Report delegation decisions and rejection management information to the CMO
Commander monthly.
2.6. DCMA INTERNATIONAL CONTRACT MANAGEMENT OFFICE FIRST LEVEL
SUPERVISOR. The assigned DCMAI CMO First Level Supervisor (FLS) must:
a. Ensure assigned FS are trained to comply with NATO STANAG 4107, AQAP-2070, the
requirements of the applicable International Agreements and any established GQA
administrative procedures.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 2: Responsibilities 10
b. Ensure assigned FS are trained to identify contractual requirements invoking ITAR/EAR
restrictions and the requirements associated with the flow down of requirements to
subcontractors.
2.7. DCMA INTERNATIONAL CONTRACT MANAGEMENT OFFICE FUNCTIONAL
SPECIALIST. The assigned DCMAI CMO FS must:
a. Comply with this Manual when requesting CAS from foreign governments under the
terms of an International Agreement and must not duplicate nor perform oversight of the CAS
surveillance performed by the HN.
b. Ensure contracts not delegated to the HN meet the exception criteria and records of these
“decisions not to delegate” are maintained.
c. Comply with the required processes of the applicable International Agreements and any
established financial services administrative procedures. Ensure complexity, breadth, and depth
of requests for financial services is fully understood before engaging with HN partners.
d. Comply with the required processes of NATO STANAG 4107, AQAP-2070, the
applicable International Agreements, and any established CAS administrative procedures. See
Resource Page for links to the applicable documents.
e. Be cognizant of export controls, ITAR/EAR, export license provisos, and ensure that CAS
requests include the requisite export control attestations as required, and are processed in
accordance with the cognizant DCMAI CMO local procedures.
2.8. COMMANDER, DCMA CONUS CONTRACT MANAGEMENT OFFICE. The
DCMA CONUS CMO Commander must:
a. Escalate potential noncompliance of the provisions of International Agreements or NATO
processes by either DoD FS or foreign government FS to the DCMA Director, DCMA Executive
Director of QA, DCMAI Functional Director, and the Commander, DCMAI through the
appropriate chain of command. The DCMAI Functional Director must be made aware of the
situation and circumstances.
b. Ensure assigned FS delegate all contracts that require GQA surveillance to the cognizant
DCMAI CMO and, do not duplicate nor perform oversight of risks/tasks delegated.
2.9. DCMA CONUS CONTRACT MANAGEMENT OFFICE FIRST LEVEL
SUPERVISOR. The assigned DCMA CONUS CMO FLS must:
a. When FS perform GQA or financial services on behalf of foreign governments under the
terms of applicable International Agreements the FLS will ensure the assigned FS comply with
this Manual. DCMA CMOs must provide services only upon receipt of a request for services
from the DoDCCP.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 2: Responsibilities 11
b. Ensure assigned FS are trained to comply with NATO STANAG 4107, AQAP-2070, the
requirements of the applicable International Agreements and any established GQA
administrative procedures as requested by delegations received through the Agency system of
record for RGQAs.
c. Ensure assigned FS are responsive to requests received from foreign governments through
the DoDCCP, and that they comply with all process suspense dates identified in this Manual,
AQAP-2070, or International Agreements.
d. Ensure assigned FS are trained to identify contractual requirements invoking ITAR/EAR
restrictions and the associated flow down of the requirements to subcontractors on outgoing
delegations.
2.10. DCMA CONUS CONTRACT MANAGEMENT OFFICE FUNCTIONAL
SPECIALIST. The assigned DCMA CONUS CMO FS must:
a. Comply with this Manual when performing CAS services on behalf of another
government under the terms of an International Agreement. Comply with this Manual and
DCMA Manual (DCMA-MAN) 2401, “Negotiation Intelligence Procedures,” when requesting
financial services on foreign contractors.
b. Comply with the applicable delegation process for requesting assistance and when
applicable, confirm that the request will serve a valid U.S. Government interest.
c. Delegate all contracts that require surveillance to the cognizant DCMAI CMO and do not
duplicate nor perform oversight of the risks/tasks delegated.
d. Comply with the required processes of NATO STANAG 4107, AQAP-2070, the
applicable International Agreement, and any established CAS administrative procedures when
cited on the request received from the DoDCCP.
e. Respond to requests received from foreign governments through the DoDCCP and comply
with process suspense dates identified in this Manual, AQAP-2070, or the applicable
International Agreement.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 3: Delegation Procedure – DCMA Contract Management Office to DCMA International
Contract Management Office 12
SECTION 3: DELEGATION PROCEDURE DCMA CONTRACT
MANAGEMENT OFFICE TO DCMA INTERNATIONAL CONTRACT
MANAGEMENT OFFICE
3.1. PROCESS STEPS.
a. The CONUS CMO FS will delegate known foreign contractor/subcontractor work to the
cognizant DCMAI CMO FS via the agency approved delegation tool. Delegations will be
limited to work covered by existing International Agreements. Exceptions to the delegation tool
include contract modifications and the process for requests for financial services which are
initiated in accordance with Section 6. The DCMAI CMO will prepare the RGQA in accordance
with AQAP-2070. The process starts with the receipt of a government contract or delegation
requiring DCMAI CAS. Initiate all requests for financial services only through the DCMAI
CMO responsible for the contractor proposal under review. CMOs must never initiate requests
or inquiries directly through the HN or audit authority of a given foreign government. Ensure
that all requests for financial services are complete, and that all required forms are completely
filled. Complete and accurate request packages are critical to provide quality reports and
mitigate foreign contractor challenges. The DCMAI CMO will not initiate a request without
accurate and complete documentation.
b. Contract Receipt and Review (CRR) must be accomplished by all FSs pursuant to
DCMA-MAN 2501-01, “Contract Receipt and Review. During the performance of CRR,
special attention must be given to the identification of contractual requirements associated with
ITAR/EAR. ITAR/EAR restrictions are a critical aspect of the CRR. During CRR if export
controls are listed in the contract, the FS will interview the contractor to discuss export licenses
and contractor safeguards of export controlled items.
c. For GQA delegations, risk assessment must be performed by QA FSs pursuant to DCMA-
MAN 2303-01, “Surveillance - Assess Risk.” Supplier performance history must be coordinated
with DCMAI CMO FSs. For detailed information concerning DCMA responsibilities related to
ITAR, see the ITAR Delegation process flowchart on the Resource Page.
d. The FS will document the surveillance plan in accordance with DCMA-INST 309,
“Government Contract Quality Assurance (GCQA) Surveillance Planning.”
e. The FS will determine the need to delegate GQA to DCMAI in accordance with DCMA-
MAN 2101-04, “Delegate Surveillance.” DCMA CMO FS must not provide additional/duplicate
CAS activities, nor perform oversight of the GQA surveillance delegated. The following
considerations must be addressed when delegating:
(1) The exceptions to using the Agency approved delegation tool are those CAS requests
which utilize the Agency system of record for RGQAs; e.g., International requests or National
Aeronautics and Space Administration (NASA) delegations. Once work is entered into and
managed by the Agency system of record for RGQAs, all further subdelegations must be issued
in the Agency system of record for RGQAs until its completion.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 3: Delegation Procedure – DCMA Contract Management Office to DCMA International
Contract Management Office 13
(2) Delegation of CAS for classified programs must be processed in accordance with
supplemental Instructions maintained by the Special Programs Command.
3.2. COORDINATION. Information addressed in paragraph 3.1.c. through 3.1.f (3), must be
coordinated by the sending FS with the receiving DCMAI FS prior to the delegation being sent.
When requested, copies of risk assessments, surveillance plans and other pertinent information
must be provided to DCMAI CMO QA FS. All export control related documents/information
(Manufacturing License Agreement (MLA)/Technical Assistance Agreement (TAA) numbers,
expiration dates, and what is being protected) must be sent with the delegation to the DCMAI
CMO.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 4: Request For Quality Assurance Procedure – DCMA International To A Foreign
Government 14
SECTION 4: REQUEST FOR QUALITY ASSURANCE PROCEDURE
DCMA INTERNATIONAL TO A FOREIGN GOVERNMENT
4.1. PROCESS INPUT/OUTPUT. The process starts with the receipt of a government
contract or delegation requiring GQA by the DCMAI CMO. The process output may be a
request for GQA to the foreign government.
4.2. CONTRACT RECIEPT AND REVIEW AND EXCEPTIONS TO REQUESTING
CONTRACT ADMINISTRATION SERVICES.
a. DCMAI CMO QA FS perform CRR pursuant to DCMA-MAN 2501-01. CRR must be
documented in a manner that complies with this Manual and the intent of DCMA-MAN 2501-
01.
b. During CRR, the DCMAI CMO QA specialist must give special attention to the
identification of contractual requirements associated with the ITAR/EAR restrictions.
ITAR/EAR restrictions are a critical aspect of the CRR when considering whether GQA can be
requested of the foreign government. For detailed information concerning DCMA
responsibilities related to ITAR/EAR, see the ITAR/EAR Delegation Process Flowchart located
on the Resource Page.
c. The CRR must include a determination as to whether exceptions exist that would preclude
DCMAI from requesting GQA services from the foreign government FS under the terms of
existing International Agreements.
d. Common exceptions include:
(1) ITAR/EAR Restrictions.
(2) Navy Special Emphasis Programs. These contracts can contain a “no-foreign” access
provision that prevents requesting GQA or financial services of the foreign government. These
are contracts identified as Level 1 Sub-Safe, Navy Nuclear Propulsion Program, etc.
(3) NASA. These International Agreements are applicable to defense products. NASA
is a non-DoD customer. With the exception of Canada, request for services for NASA contracts
are not authorized.
(4) Coast Guard. This is a non-DoD customer. With the exception of Canada, request
for services for Coast Guard contracts of the HN are not authorized.
(5) Foreign Military Sales (FMS) Contracts. In order to avoid conflicts of interest,
services for U.S. FMS contracts will not be requested of a third party (not a party to the contract)
foreign government without the coordination and consent of the foreign government’s focal point
prior to issuing a request for a GQA. DCMAI CMO QA FS must identify the FMS customer so
that an acceptance decision can be made. All coordination and acceptance decisions must be
documented. The third party foreign government has the right to decline the request for GQA.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 4: Request For Quality Assurance Procedure – DCMA International To A Foreign
Government 15
(6) No International Agreement. The exchange of GQA is limited to foreign
governments with whom the U.S. has an agreement for the reciprocal exchange of such services.
(7) Low Risk. GQA services for low risk contracts (defined in DCMA-PTM 19-003,
“Workload Acceptance”) are not normally requested of the foreign government. However,
requests may be used to establish initial risk levels or to occasionally revalidate risk decisions.
(8) Cost Effectiveness. When the International Agreement is a fee-for-service
arrangement, the FS must consider the cost effectiveness of requesting the required GQA
services from the foreign government. Where it is more cost effective for DCMAI FS to perform
the required surveillance, the information used to make such a decision must be documented on
the GQA surveillance plan.
(9) Time Constraints. Time constraints are related to contract period of performance
(normally less than 45 days). In many cases, the contractually required delivery date does not
allow sufficient time to plan, prepare, and process an RGQA to the foreign government’s GQA
focal point and sufficient time for the foreign government FS to adequately develop and execute
a GQA surveillance plan.
(10) Other Exceptions. Unresolved issues warranting non-delegation to the foreign
government; (e.g., issues dealing with non-acceptance, resources), must be escalated through
command channels to the DCMAI Commander through the DCMAI Functional Director on the
DCMAI Command staff.
e. In cases where exceptions prevent GQA from being requested of the HN, DCMAI CMO
QA FS must perform the required GQA surveillance activities in accordance with the applicable
QA Instructions/Manuals. The CMO HN Coordinator (HNC) or designated representative must
report exception codes on a monthly basis.
f. In the event a request is rejected by a HN, the CMO FS must document the reason for
rejection on the surveillance plan and comply with the procedures contained in paragraph 4.8.
4.3. PERFORM RISK ASSESSMENT AND PREPARE RISK IDENTIFICATION,
ASSESSMENT AND COMMUNICATION FORM.
a. DCMAI CMO QA must perform risk assessment pursuant to DCMA-MAN 2303-01. The
purpose of the risk assessment is to identify risk statements and the potential risk causes to the
U.S. Government that can be mitigated through GQA surveillance, regardless of who performs
the GQA surveillance. The use of the Risk Profile and Plan (RPP) is mandatory. A GCQA
surveillance plan is mandatory. However, the GCQA surveillance plan portion of the RPP form
and the Data Collection and Analysis (DCA) Plan form are optional. For sub-tier supplier
locations with letters of delegation requesting to verify, perform, or witness specific tasks only,
the development of a risk assessment/surveillance plan is not required. In such cases, the list of
activities specified in the delegation serves as the surveillance plan.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 4: Request For Quality Assurance Procedure – DCMA International To A Foreign
Government 16
b. Risk statements and risk causes identified as a result of the risk assessment must be
documented on the DCMA Risk Profile and on the Risk Identification Assessment and
Communication (RIAC) form. The RIAC is one of the forms used to request GQA services from
the HN. Risk statements and risk causes documented on the RIAC to the HN must be traceable
to the Risk Profile.
(1) The risk statement generator provides a risk impact rating for each risk impact
indicator. The risk impact rating documented on the Risk Profile must be transferred to the
equivalent and corresponding risk impact rating on the RIAC form. A high rating on the Risk
Profile is equivalent to a 9 rating on the RIAC; a moderate rating is equivalent to a 4 rating; and
a low rating is equivalent to a 1 rating. (See Figure 1, RIAC Form Example.)
(2) The likelihood of the risk cause occurring, documented on the Risk Profile, must be
transferred to the equivalent and corresponding risk likelihood rating on the RIAC form. A high
rating on the Risk Profile is equivalent to a 9 rating on the RIAC; a moderate rating is equivalent
to a 4 rating; and a low rating is equivalent to a 1 rating. (See Figure 1, RIAC Example.)
Figure 1. Risk Identification Assessment and Communication Form Example
(3) The risk statement and cause(s) identified on the RIAC form are assigned a risk index
number using the risk index matrix of AQAP-2070, Annex C. The risk index is calculated
mathematically as Impact x Likelihood (I x L). Figure 2, Risk Index of AQAP-2070, is an
excerpt from AQAP-2070. Product criticality is taken into consideration when determining the
risk impact and the risk index. Refer to the information in AQAP-2070 Annex C, paragraph
C.3.4.3.1, Product Criticality.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 4: Request For Quality Assurance Procedure – DCMA International To A Foreign
Government 17
Figure 2. Risk Index of AQAP-2070
c. High-risk impact indicators identified on the Risk Statement Generator Form; i.e., Critical
Safety Items (CSI), Air Launch and Recovery Equipment (ALRE) CSI, must have the specific
details of the high impact identified on the RIAC.
(1) Each critical characteristic and/or important manufacturing process identified as CSI
or ALRE CSI must be documented as an individual risk cause on the RIAC under an overarching
risk statement associated with the high impact. See Resource Page for Delegation Clarification
for Issuance, Rejection, and Acceptance to CMO’s document.
(2) These high-impact indicators must be reflected as a number nine (9) on the impact
rating on the RIAC and the risk index matrix in Figure 3.
d. Information necessary to complete the performance factors assessment may not be readily
available on the first request associated with a particular supplier. The DCMAI FS will contact
the HN Government Quality Assurance Representative (GQAR) for assistance in gathering
information to identify risk causes. Do not send the performance factors form to HN FS for
completion. See Resource Page for Delegation Clarification for Issuance, Rejection, and
Acceptance to CMO’s document.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 4: Request For Quality Assurance Procedure – DCMA International To A Foreign
Government 18
(1) During the course of the GQA surveillance, supplier performance information must
be communicated with the HN FS and records related to the supplier’s performance must be
maintained for future delegations. See Resource Page for Delegation Clarification for Issuance,
Rejection, and Acceptance to CMO’s document.
(2) The performance factor form is an excellent tool to use during occasional status
meetings or other communication with the HN QA FS when discussing supplier performance.
See Resource Page for Delegation Clarification for Issuance, Rejection, and Acceptance to
CMO’s document.
e. Customer mandatory requirements identified by a Quality Assurance Letter of Instruction
(QALI) must be attached to the RGQA by the DCMAI FS with a single risk statement
“Customer Mandatory Requirement” and the risk cause(s) documented on the RIAC is the
individual mandatory requirement of the QALI.
f. Risk assessments must be revised by the DCMAI FS as the supplier’s performance history
changes or as new risk information becomes available. As a minimum, risk assessments must be
reviewed on an annual basis and the risk profile and RIAC revised as necessary. The annual
review due date must be documented on the GQA surveillance plan.
(1) DCMA surveillance plans and active requests (RGQAs/RIACs) to the HN must be
revised as a result of the updated risk assessment or changes in the supplier performance.
(2) HN assistance must be requested in order to validate information used in determining
the low risk rating.
g. When new contracts or delegations are received and after the risk assessment is
performed, it may be determined that the current RGQA and RIAC forms do not accurately
reflect the applicable risk statements and causes. In such cases, a revised RGQA, and if
applicable, a revised RIAC, are required to be sent to the HN focal point. Send the new
contract/subcontract/or contract number to the HN’s focal point. If the contract is to be provided
by the supplier, advise the HN focal point of the contract number, the applicable RGQA/RIAC,
and the applicable contractual clause that requires the supplier to provide a copy of, or access to,
the contract by the Government.
h. For those nations not using the processes defined in AQAP-2070, DCMA FS must
document the results of the risk assessment on the RGQA forms and follow the process
identified in the applicable International Agreement and/or associated GQA administrative
procedure.4.4. PREPARE THE SURVEILLANCE PLAN.
a. DCMA-MAN 2303-01 and DCMA-MAN 2303-02, “Surveillance – Plan Events,” must be
used to identify and document GQA activities, methodologies, and/or techniques used to reduce
the likelihood of risk causes occurring and to establish a basis of confidence that the supplies
meet the quality and technical requirements of the contract.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 4: Request For Quality Assurance Procedure – DCMA International To A Foreign
Government 19
b. Surveillance plans must be maintained by DCMA FS regardless of who performs the
GQA surveillance (DCMA or HN FS). In the event that a delegation is not a “high risk,” a
DCMA generated surveillance plan showing traceability to a delegation will be considered
adequate documentation of a surveillance plan.
c. All coordination and communication between DCMAI and HN FS concerning CSI, low-
risk surveillance strategies, etc., must be documented on the DCMA surveillance plan, including
the results of the communication.
d. Contracts or subcontracts not delegated to the HN and rationale for not requesting GQA
services must be documented on the GQA surveillance plan.
e. Information concerning risk statements or risk causes not accepted or partially accepted
by the HN must be documented on the GQA surveillance plan.
f. Identification of all contracts or subcontracts covered by a facility-wide RGQA and the
estimated contract final delivery date must be an attachment (notification letter, see Resource
Page) and maintained as part of the RGQA. This information must be used to update the HN QA
FS of active GQA work under the current facility-wide RGQA.
g. DCA strategy must be identified on the GQA surveillance plan. DCA must be performed
pursuant to DCMA-MAN 2303-04, “Surveillance – Document Results, Corrective Actions and
Provide Feedback.” DCMA risk assessments, surveillance plans, and active requests
(RGQAs/RIACs) must be revised as a result of data analysis.
4.5. FACILITY-WIDE REQUEST FOR GOVERNMENT QUALITY ASSURANCE.
a. DCMAI CMO QA may use facility-wide RGQAs where suppliers have multiple contracts
for like or similar items utilizing similar manufacturing processes to optimize resources. If
DCMAI has an existing request, there is no need to generate additional RGQAs for similar
contracts with the same supplier. Though ITAR related delegations are not prohibited from
being placed on facility-wide delegations, they are not recommended. Any decisions for ITAR
facility-wide delegations need to be considered on a case-by-case basis in order to ensure all
ITAR delegation controls are maintained. In addition to the standard requirements for facility-
wide delegations the reporting, and communicating status of the delegation would be required on
a more frequent basis (i.e., as contract/MLA/TAA expiration dates are met or revised).
Additional information needed to be tracked and communicated would include:
• Contract number and associated final delivery date
• MLA/TAA license numbers and associated expiration dates
• Description of defense article, service, technical data being controlled
b. DCMAI CMO QAs using the facility-wide approach to requesting GQA require only one
documented Risk Profile and one Surveillance Plan to be developed covering all contracts under
the purview of the facility-wide RGQA.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 4: Request For Quality Assurance Procedure – DCMA International To A Foreign
Government 20
c. Each CMO requesting GQA on a facility-wide basis must develop a documented process
for identifying, tracking, and reporting current contracts applicable to a single supplier facility-
wide RGQA. As a minimum, the report must be updated and provided to the HN QA FS on an
annual basis during the annual review of the RGQA and RIAC (if applicable), unless a shorter
timeframe is agreed upon with the HN. The frequency of reporting must be documented on the
GQA surveillance plan.
d. The report must show applicable contracts and subcontracts and the estimated contract
final delivery date.
(1) For purposes of facility-wide RGQA reporting, except ITAR, the estimated contract
final delivery date shown on the DCMA facility-wide report must also be considered as the
RGQA closure date. Unless the report is updated or otherwise revised, this is the date the HN
QA FS must cease GQA surveillance efforts and consider the request closed. A GQA Closure
Report (GQACR) with an updated RIAC must be requested if one had not been received. If
delivery dates change, DCMA QA FS must ensure the estimated completion date is updated on
the DCMA facility-wide report.
(2) Requesting individual GQACR for contracts under the purview of a facility-wide
RGQA is not practical or desirable and must not be requested. The facility-wide RGQA must
request the HN QA FS to:
(a) Reconcile and agree with the data provided on the facility-wide report.
(b) Provide a RIAC status report indicating by contract or subcontract, when
applicable, any increases or decreases in risk status. The frequency of reporting must be agreed
to via the RGQA and documented in the GQA surveillance plan.
(c) Provide copies of any Corrective Action Requests (CAR) by contract issued by
the HN QA FS.
4.6. PREPARE REQUEST FOR GOVERNMENT QUALITY ASSURANCE.
a. DCMAI CMO QA FS must communicate often and work closely with their HN
counterparts in establishing a teaming relationship. This relationship must be the conduit by
which information and data are exchanged regarding risks and by which confidence is reinforced
in the cooperative contract management effort. Occasional joint visits to supplier facilities by
DCMAI QA FS, when possible, must be considered to elevate the visibility of supplier
performance risks and to foster the teaming relationship and communication between the two
GQA organizations. These visits must not be to duplicate or oversee the GQA surveillance
performed by the HN. The DCMAI CMO QA Supervisor will make the final decision on
whether to make a visit or not.
b. Prior to requesting GQA for CSI characteristics, the DCMAI CMO QA FS must
coordinate with the HN QA FS to determine if a GQA surveillance strategy can be developed
that will meet the intent of the DCMA CSI Instructions. For HNs, the term “critical safety
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 4: Request For Quality Assurance Procedure – DCMA International To A Foreign
Government 21
items” may have different implications than in DCMA; therefore, the term “critical safety items
(or CSI)” must be clarified with the HN using their specific term, such as “critical items” during
these discussions. This will provide the HN with an understanding of the high impact risk
designation. DCMAI CMO FS comply with the terms used in AQAP-2070 and/or in the
individual International Agreement, including any GQA administrative procedures.
c. Only the minimum GQA surveillance necessary to mitigate the identified risk causes and
to provide confidence in a supplier’s ability to provide contractual supplies or services must be
requested of the HN QA FS. DCMAI CMO QA FS must coordinate with HN QA FS to develop
an appropriate GQA surveillance interval (quarterly, semi-annual, annual, etc.) when requesting
GQA for non-complex, non-critical products, or other low risk activities. DCMA FS must not
duplicate nor perform oversight of the GQA surveillance performed by the HN QA organization.
d. When identifying the contractual QA standard on the RGQA, DCMAI CMO QA FS must
not cite an “equivalent” AQAP standard on the RGQA. Only the QA standard required by the
contract will be referenced on the RGQA.
e. The RGQA must be prepared in accordance with AQAP-2070 for all NATO nations with
International Agreements for exchanging GQA services and for those non-NATO nations using
the Mutual GQA processes of AQAP-2070, as ratified by a GQA administrative procedure. (See
the Resource Page for a copy of the mandatory and optional forms.) For those nations not using
the AQAP-2070 processes, DCMA FS must use the RGQA forms identified in the International
Agreement and associated GQA administrative procedure. (See the Resource Page for samples
of RGQA forms used by non-NATO nations.)
f. The DCMAI CMO QA must clearly identify the authority and responsibility of the HN
QA FS concerning the following areas:
(1) CARs. Pursuant to AQAP-2070, paragraph A.2.1., HN national practice will dictate
the specific actions of the GQA participants. To comply with DCMA-INST 1201, “Corrective
Action Process,” DCMA QA FS assigned to the CMO cognizant of the prime must issue the
CAR to the prime supplier. DCMAI CMO QA FS must request copies of any CARs issued by
the HN and will be responsible for entering the CAR into the Agency system of record for CAR.
DCMAI CMO QA FS will gain an understanding of HN’s corrective action process to enable
appropriate communications with the HN QA FS; i.e., using HN’s terminology vice DCMA’s on
RGQAs or during e-mail or telephone communication.
(2) Deviation Permits and Concessions (Permission to depart from the originally
specified contract requirements of a product prior to realization.). Identify whether HN QA FS
are authorized to concur or nonconcur with the classification/disposition of the supplier’s minor
deviation permits and/or concessions. Authority for major deviation permits and/or concessions
are never delegated to the HN QA FS; however, indicate whether recommendations or comments
are requested. See DCMA-MAN 2301-06, “Discrepancy Processing,” for the detailed process.
See Resource Page for Delegation Clarification for Issuance, Rejection, and Acceptance to
CMO’s document.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 4: Request For Quality Assurance Procedure – DCMA International To A Foreign
Government 22
(3) CSI. Request HN QA FS contact DCMAI QA FS (Delegator) prior to issuing
subcontractor delegations related to CSI.
(4) Subcontractor Delegations. Request HN QA FS contact DCMAI QA FS (Delegator)
prior to issuing subcontractor delegations to another country so that DCMA can determine if
reciprocal no-charge agreements exist between the U.S. DoD and the third party nation.
(5) Surveillance Plans. Request copies of the HN GQA surveillance plans for contracts
that contain CSI, or other high-impact Risk Statements or high-likelihood Risk Causes. DCMAI
QA FS will review the HN GQA surveillance plan to ensure all risk causes and GQA activities
identified on the RIAC and RGQA have been addressed on the plan. See Resource Page for
Delegation Clarification for Issuance, Rejection, and Acceptance to CMO’s document.
(6) Facility-Wide Delegations. Where suppliers have multiple contracts for like or
similar items utilizing similar manufacturing processes, facility-wide delegations are encouraged
to optimize resources.
(7) Reporting. DCMAI FS must recognize that the HN QA FS’s primary task is the
performance of GQA; therefore, reporting requirements will be proportional to the risks related
to the program, contract, or supplier performance. Reporting requirements must be kept to a
minimum.
(8) Product Release and Delegation Completion. Include any special instructions related
to releasing the product from the supplier’s facility and for completing the delegation.
(9) Risk Status Reporting. The RGQA must state whether a risk status report is
requested from the HN on an ongoing basis for long-term delegations. A risk status report, such
as a RIAC, must always be requested at completion of GQA.
g. ITAR/EAR Restrictions. Where the contract or subcontract contains ITAR/EAR
restrictions, the RGQA must be prepared and processed using the procedures in Section 10.
ITAR/EAR-specific RGQA forms must be used to request HN GQA services when access to
ITAR/EAR information is authorized. See the process flowchart for ITAR/EAR RGQAs on the
Resource Page for the required forms.
4.7. FORWARD REQUEST FOR GOVERNMENT QUALITY ASSURANCE TO
APPLICABLE HOST NATION FOCAL POINT.
a. The DCMAI CMO QA must send the RGQA and RIAC (as applicable) electronically to
the HN’s focal point identified in NATO STANAG 4107, Annex A, or in the individual
International Agreement. The RGQA and RIAC, as applicable, must be sent in sufficient time
for the HN QA FS to process the request through their command channels and to adequately plan
and execute the necessary GQA surveillance activities.
b. The NATO Delegation Feedback (DFB) form is used to provide information concerning
the quality of the Mutual GQA process so that both the Delegator and the Delegatee can use the
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 4: Request For Quality Assurance Procedure – DCMA International To A Foreign
Government 23
information to improve the quality of their respective services within the Mutual GQA process.
When completion of a DFB form is requested and submitted with an RGQA, the HN QA FS will
provide feedback information to the DCMAI CMO QA FS concerning the quality of the
information provided on the RIAC and RGQA.
(1) DCMA FS must send a DFB form as an attachment to the RGQA.
(2) DCMA FS must use the information provided on the DFB form to improve the
quality of the information provided on future RIAC forms and RGQAs.
4.8. MANAGING REJECTED REQUEST FOR GOVERNMENT QUALITY
ASSURANCE.
a. When RGQAs are formally rejected by the HN, the HNC, or designated representative,
must report rejected reason codes and rejection management codes on a monthly basis via the
established performance indicator metric in the Agency system of record. (See the Resource
Page for rejection codes.)
b. The HNC must manage rejected delegations by identifying how the CMO will cover the
workload that was rejected by the HN. Comments must be provided that will detail whether the
actions being taken will manage the workload temporarily or permanently. (See the Resource
Page for codes to be used for reporting.)
c. If applicable, the HNC must discuss rejects with the respective HNs to determine what
actions may be necessary to resolve the issue. All communications must be copied to the
DCMAI Functional Director. The DCMAI Functional Director will report and discuss rejects
during NATO Working Group 2 for Quality meetings.
4.9. PERFORM PRODUCT ACCEPTANCE AND RELEASE.
a. Pursuant to DCMA-INST 2101, “Product Acceptance and Proper Payment,” DCMAI
CMO QA FS must accept supplies/services offered by the supplier when there is a basis of
confidence that the supplies/services conform to contract requirements.
b. GQA surveillance activities planned and implemented by the HN QA FS, based on the
risk statements and risk causes identified by DCMAI CMO QA FS, as well as other delegated
GQA activities, serves as the basis of confidence that the supplies or services conform to contract
requirements.
c. Method(s) for accepting and releasing product from the supplier’s facility must be
identified during CRR and must be annotated on the RGQA to the HN.
4.10. RECEIVE GOVERNMENT QUALITY ASSURANCE CLOSURE REPORT/RISK
IDENTIFICATION ASSESSMENT AND COMMUNICATION FORM AND MAINTAIN
RECORDS.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 4: Request For Quality Assurance Procedure – DCMA International To A Foreign
Government 24
a. For NATO nations required to use the AQAP-2070 process and those non-NATO nations
having elected to use the AQAP-2070, completion of the requested GQA is indicated by receipt
of a GQACR from the HN GQAR. The GQACR is to be submitted to the DCMAI CMO QA FS
from the HN GQAR within 20 working days of completion of the RGQA.
b. If requested reports have not been received, the DCMAI CMO QA will contact the HN
GQAR and remind them of the report requested on the RGQA. On the second attempt for the
information the HNC will send the request to the HN’s CCP and include a DFB. Communicate
information relative to previous requests for the report or other information requested on the
RGQA.
c. As part of the closure process, the HN GQAR must consider whether the status of the
risks, as stated on the current RIAC form, has increased, decreased, or remained stable as a result
of GQA surveillance activities performed in support of the RGQA.
(1) Where risk status has changed, the HN GQAR must make recommendations to
DCMAI QA FS regarding future requests for GQA.
(2) Where a risk status update at RGQA closure has been requested on the RGQA but
has not been received, the DCMAI CMO QA FS must contact the HN GQAR and request an
updated RIAC. If still not received within a reasonable timeframe, a DFB form must be
processed via the HNC through the HN focal point with a written request for an updated RIAC.
(3) Delegator satisfaction data is collected by means of the DFB form. Where the HN
has requested DFB from DCMAI, the DFB form must be completed and returned to the HN QA
organization within 10 working days.
(4) Copies of all DFB forms, either received from or sent to the HN’s QA organization,
must be provided to the CMO HNC who must maintain DFB records for process improvement
purposes.
d. Records Retention. Records must be maintained in accordance with DCMA-MAN 4501-
04, “Records Management,” and as required by the specific process instructions. In addition,
each DCMAI CMO operating under the purview of an International Agreement must maintain
files that include:
Results of CRR, including exceptions to delegations in the Agency system of record for
CRR
Active and completed RGQA forms
Active and completed RIAC forms
GQACRs
Records of communication concerning delegation of FMS contracts
Records related to supplier performance information obtained from the HN QA FS
regardless of media used; i.e., reports, surveillance records, telephone conversations
DFBs
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 4: Request For Quality Assurance Procedure – DCMA International To A Foreign
Government 25
4.11. CLOSE CONTRACT DELEGATION.
a. Upon receipt of the GQACR or other notification of GQA completion, DCMAI CMO QA
FS must close the RGQA in the system used for tracking and managing RGQAs to the HN.
b. If the RGQA was based on a subcontract delegation received from another DCMA CMO,
the delegation must be closed in the Agency system of record for Delegation or the Agency
system of record for RGQAs, as applicable. DCMAI CMO QA FS must inform the delegating
DCMA office of delegation completion and communicate any lessons learned not already
identified.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 5: Governement Quality Assurance Performance – Foreign Government 26
SECTION 5: GOVERNMENT QUALITY ASSURANCE PERFORMANCE
FOREIGN GOVERNMENT
5.1. PROCESS INPUT/OUTPUT. The process starts with the receipt of an RGQA from the
DCMAI CMO by the HN and the output is a GQACR provided to the DCMAI Delegator.
5.2. GOVERNMENT QUALITY ASSURANCE PERFORMANCE BY THE HOST
NATION QUALITY ASSURANCE ORGANIZATION.
a. HN organizations with whom DoD exchanges GQA services have agreed to comply with
the processes defined in the individual International Agreement and/or in NATO STANAG 4107
and AQAP-2070.
b. As such, HN GQA organizations are fully expected to plan, execute, and document all
GQA activities performed in support of the DCMAI RGQA per AQAP-2070, or the applicable
International Agreement and GQA administrative plan. The HN GQA organizations are
expected to:
(1) Acknowledge receipt of the RGQA within 5 working days of receipt.
(2) Accept, partially accept or reject the RGQA within 20 working days of receipt.
(3) Comply with all GQA tasks/activities identified on the RGQA, including reporting
requirements.
5.3. GOVERNMENT QUALITY ASSURANCE CLOSURE REPORT. When the HN
GQAR considers the RGQA performance complete and the delegation is considered closed, the
HN GQAR will conduct a records review and forward a GQACR to the DCMAI delegator
within 20 working days of completion in accordance with AQAP-2070.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 6: Request For Financial Services – DCMA International To A Foreign Government 27
SECTION 6: REQUEST FOR FINANCIAL SERVICES
DCMA INTERNATIONAL TO A FOREIGN GOVERNMENT
6.1. FOREIGN AUDIT SERVICES REQUESTS (Canada).
a. Foreign field pricing and assist audit requests for all Canadian contractor (Prime or
subcontractor) may be initiated by an internal (DCMA) requestor, an external (non-DCMA
government activity) requestor, or a contractor. All requests must be received in writing and in
accordance with DFARS 225.870, DFARS “Procedures, Guidance and Information,” (PGI)
225.870-1, DFARS PGI 225.870-5 and DCMA-MAN 2401-01, “Negotiation Intelligence
Procedures.”
b. All pre- and postaward requests are managed by the DCMA Americas CMO and all audit
services are conducted by the Canadian audit authority. More information can be found on the
Resource Page.
c. Pre-award foreign audit service requests include, but are not limited to: rat e, technical,
and full proposal reviews, commercial item determinations, labor time and recording systems
reviews, and rate verifications.
d. Postaward foreign audit service requests include, but are not limited to: reviews in
support of contracting officer negotiations, termination settlements, final incurred cost audits,
and contract closeout reviews.
e. Upon identification of the need for foreign pricing services involving foreign contractors,
the DCMAI requestor must validate a bona fide need for the review. More information on
validating bona fide need can be found in DCMA-MAN 2401-01, paragraph 4.2.b.
f. All requestors must submit requests for foreign contractor financial service in accordance
with the forms and guidance provided in the “Foreign Contractor Field Pricing and Assist Audit
Information Sheet” located on the Resource Page.
g. Export controlled data is subject to the limitations outlined in Section 10 of this Manual
and as outlined in paragraphs 2.7. and 2.8. of this Manual.
h. Proposal documents and file sizes too large to be sent through email will be transmitted
via other approved secured means (i.e., Secure File Transfer, etc.).
6.2. PERFORM THE REQUESTED FOREIGN CONTRACTOR PRICING
ASSISTANCE DCMA INTERNATIONAL CONTRACT MANAGEMENT OFFICE
(CANADA)
a. The DCMA Americas responsible official will establish and manage foreign contractor
pricing requests in accordance with current Reciprocal Defense Procurement (RDP) and
Acquisition Policy Memorandum of Understanding (MOU), also referred to as RDP or HN
Agreement, while considering the procedures outlined in DCMA-MAN 2401-01 and will employ
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 6: Request For Financial Services – DCMA International To A Foreign Government 28
those instructions to the maximum extent practicable, to include the use of the Agency
authorized capability. The link to the current RDP is found on the Resource Page.
b. Once the DCMA Americas responsible official is in receipt of a complete request, and
when applicable, valid U.S. Government interest has been confirmed, he/she will create a case
file and initiate contact with the Canadian audit authority.
c. The Canadian Audit Authority (CAA) will review the documentation and work with the
DCMA Americas responsible official regarding any issues that require further information or
clarification.
d. Due to Canadian audit procedures, a due date cannot be established until the audit
authority has reviewed and assigned the request. Until that time, the DCMA Americas
responsible official will provide a preliminary estimated completion date (ECD) to the requestor.
A firm ECD will be provided to the requestor once the lead auditor conducting the review has
reviewed the request and provided an update to DCMA Americas.
e. Upon receipt of the CAA final audit product, the DCMA Americas responsible official
will review the report, transmit to the requestor, and provide further support with regard to
follow-on clarifying questions. A redacted example of a standard CAA final audit product can
be found on the Resource Page.
6.3. PERFORM REQUESTED FOREIGN CONTRACTOR PRICING ASSISTANCE
FOREIGN GOVERNMENT (Canada).
a. Pre-award Reviews.
(1) The U.S. Government relies upon the CAA to perform reviews of proposals
submitted by Canadian suppliers that are subcontracting to a U.S. Government prime contractor
as well as contracts placed directly with Canadian suppliers in accordance with DFARS PGI
225.870-1.
(2) The Canadian Assist Audit Coordinator reviews and assigns the DCMA Americas
request to a specialist who conducts an analysis, makes a determination of fair and
reasonableness, and generates a report.
(3) The CAA's output document is referred to as a “Supplier Proposal Certification
Report.” This high-level report indicates which elements were assessed, brief points on the
methods of assessment, and confirmation that the CAA stands behind the proposal as fair and
reasonable, were the same requirement awarded by the Government of Canada, as well as any
price changes that have occurred as a result of the analysis conducted.
(4) If the CAA is unable to certify the proposal (or elements thereof) as fair and
reasonable, the report will so state. It is then a decision of the U.S. Government to proceed with
award, or open discussions with the Canadian supplier.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 6: Request For Financial Services – DCMA International To A Foreign Government 29
(5) The Supplier Proposal Certification Report will serve as sufficient documentation for
the procurement file that due diligence has been conducted.
b. Postaward Reviews.
(1) Postaward audits are conducted by the Canadian audit authority’s Assurance Services
Group, a group of professional accountants who provide audit and assurance-related services in
support of procurement and contract administration activities.
(2) Assurance services are conducted in accordance with the Canadian audit authority’s
Acquisitions Branch Contract Assurance Standards (ABCAS), which have been developed
specifically for the performance of assurance engagements on Canadian Government contracts.
These ABCAS are comparable to the U.S. Government Accountability Office’s Generally
Accepted Government Auditing Standards (GAGAS).
(3) The assurance engagement report is the principal means of conveying the results of
the postaward review. The resolution of engagement findings and results are the responsibility
of the applicable U.S. contracting authority.
6.4. FOREIGN CONTRACTOR PRICING REQUESTS (OTHER THAN CANADA)
a. Foreign field pricing and assist audit requests for foreign contractors may be initiated by
an internal (DCMA) requestor, an external (non-DCMA government activity) requestor, or a
contractor. All requests must be received in writing and accordance with DFARS 225.870, PGI
225.870-1 and PGI 225.870-5 and DCMA-MAN 2401-01.
b. All pre and post award requests are managed by the DCMAI CMO designated in the
“Foreign Contractor Field Pricing and Assist Audit Information Sheet” located on the Resource
Page, and will be conducted by HNs with reciprocal audit service agreements or program
cooperative agreements, Defense Contract Audit Agency (DCAA), or a DCMA Cost/Price
Analyst as applicable.
c. Pre-Award foreign pricing service requests include, but are not limited to: full proposal
reviews, labor, time and material, and rates and factors reviews.
d. PostAward foreign pricing service requests include, but are not limited to: reviews in
support of contracting officer negotiations, termination settlements, final incurred cost audits,
contractor business system reviews, and contract closeout reviews.
e. Upon identification of the need for foreign pricing services involving foreign contractors,
the DCMAI requestor must validate a bona fide need for the review. More information on
validating bona fide need can be found in DCMA-MAN 2401-01, paragraph 4.2.b.
f. All requestors must submit all foreign contractor requests in accordance with the forms
and guidance provided in the “Foreign Contractor Field Pricing and Assist Audit Information
Sheet” located on the Resource Page.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 6: Request For Financial Services – DCMA International To A Foreign Government 30
g. Export controlled data is subject to the limitations outlined in Section 10 and as outlined
in responsibilities paragraphs 2.7. and 2.8. of this Manual.
h. Proposal documents and file sizes too large to be sent through email will be transmitted
via other approved secured means (i.e., Secure File Transfer, etc.).
6.5. PRE-AWARD FOREIGN CONTRACTOR PRICING-REQUEST FROM DCMA
CONTRACT MANAGEMENT OFFICE, EXTERNAL CUSTOMER, OR
CONTRACTOR (OTHER THAN CANADA)
a. The DCMAI Cost/Price Analyst will establish and manage foreign contractor pricing
requests in accordance with current Reciprocal Defense Procurement and Acquisition Policy
MOU, also referred to as RDP or HN Agreement, while considering the procedures outlined in
DCMA-MAN 2401-01, to include the use of the Agency authorized capability. The link to the
current RDP is found on the Resource Page.
b. Once bona fide need has been established and the DCMAI Cost/Price analyst is in receipt
of a complete request package he/she will create a case file in accordance with current Agency
and CMO policies and procedures and initiate contact with the foreign audit authority, DCAA, or
the contractor as appropriate.
c. The cognizant foreign audit authority, DCAA, or DCMAI Cost/Price Analyst will review
the documentation and work with the DCMAI Cost/Price Analyst or initial requestor regarding
any issues that require further information or clarification, as applicable.
d. Firm due dates cannot be established until the cognizant foreign audit authority has
reviewed and assigned the request. Until that time, the DCMAI Cost/Price Analyst will provide
a preliminary ECD to the requestor that is in line with the current due date as applicable to each
foreign HN. A firm ECD will be provided to the requestor once one has been provided to
DCMAI.
e. Upon receipt of the final audit product provided by the foreign audit agency, DCAA, or
completed by DCMAI, the DCMAI Cost/Price Analyst will transmit to the requestor, and
provide further support with regard to follow-on clarifying questions if necessary.
6.6. PERFORM REQUESTED FOREIGN CONTRACTOR PRICING ASSISTANCE-
FOREIGN GOVERNMENT (OTHER THAN CANADA)
a. Pre-Award Reviews.
(1) The U.S. Government relies upon foreign HN audit agencies, DCAA, and DCMAI to
perform reviews of proposals submitted for foreign suppliers that are subcontracting to a U.S.
Government prime contractor as well as contracts placed directly with foreign suppliers in
accordance with DFARS 225.872-6 and DFARS PGI 225.872-6.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 6: Request For Financial Services – DCMA International To A Foreign Government 31
(2) The foreign HN audit agencies, DCAA, or DCMAI, as applicable, reviews and
assigns the request to a specialist who conducts an analysis, makes a recommendation of fair and
reasonableness, and generates a report.
(3) The foreign HN audit agencies, DCAA, or DCMAI output document is a report
which documents the elements assessed per the original request, brief points on the methods of
assessment, questioned costs, and any recommendations as a result of the analysis conducted.
b. Postaward Reviews.
(1) Postaward audits are conducted by the foreign HN audit agencies, DCAA, or
DCMAI as applicable, who provide audit and assurance-related services in support of
procurement and contract administration activities.
(2) The final report is the principal means of conveying the results of the postaward
review. The resolution of findings and recommendations are the responsibility of the applicable
U.S. contracting authority.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 7: Request For Government Quality Assurance Procedure – Foreign Government To
Department of Defense Central Control Point 32
SECTION 7: REQUEST FOR GOVERNMENT QUALITY ASSURANCE
PROCEDURE FOREIGN GOVERNMENT TO DEPARTMENT OF
DEFENSE CENTRAL CONTROL POINT
7.1. PROCESS INPUT/OUTPUT.
a. This section describes the RGQA procedures that will be used when a foreign government
requests DCMA perform a GQA on defense products at suppliers located within the U.S. When
a foreign government or international organization submits a CAS request involving a direct
commercial sales contract, it will be sent to the DoDCCP. Upon receipt of a request for CAS,
the DoDCCP will follow the DFARS PGI 242.002, “Interagency Agreements.” The DoDCCP is
responsible for validating the work against existing International Agreements. Once validated,
the DoDCCP will input the request into the Agency system of record for RGQAs and route it to
the applicable CONUS CMO. In the event that a re-delegation back to the requesting foreign
nation is necessary, the CONUS CMO will send the request through the Agency system of
record for RGQAs. This Agency system of record for RGQAs delegation will be routed back to
the DCMAI CMO responsible for work in the requesting foreign nation. In turn, the DCMAI
CMO will forward this re-delegation back to the requesting HN focal point pursuant to existing
International Agreements.
b. For the foreign government, the process starts when they decide that their defense contract
or subcontract requires GQA to be performed and the supplier is located within the U.S. The
output of the foreign government’s portion of this process is an RGQA sent to the U.S. DoDCCP
for performance in the U.S. by DCMA.
7.2. ALLIED QUALITY ASSURANCE PUBLICATION-2070/INTERNATIONAL
AGREEMENT/GOVERNMENT QUALITY ASSURANCE ADMINISTRATIVE
PROCEDURE REQUIREMENTS.
a. The following process information is provided to clarify expectations for DCMA CMO
QA FS of the foreign government’s requirements as defined in AQAP-2070, the applicable
International Agreement, and established GQA administrative procedures.
(1) Risk Identification and Assessment. The request must be risk-based. An assessment
must have been performed to identify risk statements and risk causes for inclusion on the RIAC
form which accompanies the RGQA. There are exceptions allowed for situations where risk
information is unavailable to the Delegator. (See AQAP-2070, paragraph 6.2.) For non-NATO
nations not using the AQAP process, the use of the RIAC or the form used to document the risks
associated with the contract may be defined in the International Agreement and/or GQA
administrative procedure.
(2) RGQA Information. The RGQA must provide sufficient information for DCMA QA
FS to perform the requested GQA. The RGQA will include any reporting requirements; i.e.,
status reports, copy of GQA surveillance plans, CARs. Information relative to product release,
subcontract delegations, deviation permits and concessions, etc. will also be included. (See
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 7: Request For Government Quality Assurance Procedure – Foreign Government To
Department of Defense Central Control Point 33
AQAP-2070, Section 7) For non-NATO nations the use of the RGQA may be defined in the
International Agreement and/or GQA administrative procedures.
b. The RGQA must be sent to the U.S. DoDCCP at DCMA Headquarters (HQ) International
and Federal Business Division (DCMA-FBR). DCMA CMOs must contact the DODCCP when
RGQAs are received directly from the foreign government prior to expending any effort on the
request.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 8: Request For Contract Administration Services Procedure – Foreign Government To
Department of Defense Central Control Point 34
SECTION 8: REQUEST FOR CONTRACT ADMINISTRATION
SERVICES PROCEDURE FOREIGN GOVERNMENT TO
DEPARTMENT OF DEFENSE CENTRAL CONTROL POINT
8.1. PROCESS INPUT/OUTPUT. Foreign governments and international organizations must
send their requests for CAS to the DoDCCP in DCMA-FBR in accordance with the applicable
International Agreement. The process starts with the receipt of a CAS request from a foreign
government. The output of this process is a request for services via the Agency system of record
for RGQAs, and closure of the Agency system of record for RGQAs request when the services
are complete.
8.2. DETERMINE IF LABOR RATES APPLY AND ENTER REQUEST INTO THE
AGENCY SYSTEM OF RECORD FOR RGQAS.
a. The policy and procedures of DCMA-MAN 4301-04, “Accounting,” must be used for
processing and managing CAS requests.
b. The DoDCCP International Contract Service Manager (ICSM) must:
(1) Determine whether the request is from a friendly foreign government or international
agency with whom the U.S. is a participant to an International Agreement for the exchange of
CAS or if the request is covered by a cooperative program agreement.
(2) Determine whether the requested services are authorized by and within the scope of
an applicable International Agreement.
(3) Determine whether the requested services are to be provided on a reimbursable or
non-reimbursable basis consistent with defense security assistance arrangements.
c. The DoDCCP ICSM must enter all requests from foreign governments or organizations
into the Agency system of record for RGQAs for processing, managing, distributing, cost
accounting, tracking, and communicating between DCMA CMOs and DoDCCP.
8.3. ACKNOWLEDGE REQUEST.
a. For GQA, the DoDCCP ICSM must acknowledge receipt of the request back to the
foreign government or organization within 5 working days of receiving the request. This action
assures the international customer is aware that DCMA has received the request and is
coordinating with the applicable DCMA CMO for surveillance planning and acceptance. The
customer knows that an acceptance decision is forthcoming.
b. For GQA, the DCMA CMO must make a decision regarding acceptance within 20
working days after acknowledgement of the request by the DoDCCP. The required RGQA
Response (RGQAR) form, updated RIAC, if applicable, and other forms used with the request to
indicate acceptance /rejection must be completed by the CMO, uploaded into the Agency system
of record for RGQAs, and forwarded to the DoDCCP. An email will be sent to the requestor and
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 8: Request For Contract Administration Services Procedure – Foreign Government To
Department of Defense Central Control Point 35
the DoDCCP notifying the customer of DCMA’s acceptance decision. The DoDCCP must track
Agency compliance with required suspense dates and initiate improvement measures.
8.4. TRANSMIT REQUEST TO DCMA CONTRACT MANAGEMENT OFFICE VIA
THE AGENCY SYSTEM OF RECORD FOR RGQAS. The DoDCCP must:
a. Coordinate with and electronically forward the request to the appropriate DCMA CMO
via the Agency system of record for RGQAs.
b. Distribute all acquisition documents and related materials to the CMO.
c. Request cost estimates from the CMO and ensure accurate reporting of hours.
d. Ensure CMO requests are accepted and the international customer notified within 20
working days after acknowledgement.
e. Coordinate with the CMO and provide the international customer with the reason requests
are not accepted or are only partially accepted.
f. Assist CMO and the international customer to resolve misunderstandings,
misinterpretations or problems in a timely manner to avoid any necessary escalation.
8.5. CLOSURE OF REQUEST. The DoDCCP must:
a. Ensure all required forms and reports have been received from the DCMA CMO and
forwarded to the international customer ensuring Agency compliance.
b. Ensure requests are properly closed in the Agency system of record for RGQAs.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 9: Request For Contract Administrative Service Procedure – Government Quality
Assurance Performance DCMA Contract Management Office 36
SECTION 9: REQUEST FOR CONTRACT ADMINISTRATIVE SERVICE
PROCEDURE GOVERNMENT QUALITY ASSURANCE
PERFORMANCE - DCMA CONTRACT MANAGEMENT OFFICE
9.1. PROCESS INPUT/OUTPUT.
a. The process starts with the receipt of a request for GQA via the Agency system of record
for RGQAs from the DoDCCP. The outputs are a GQACR and updated RIAC provided to the
foreign government and closure of the Agency system of record for RGQAs delegation.
b. The GQA activities must be performed in accordance with the referenced DCMA
Instructions/Manuals and, where applicable, in conjunction with AQAP-2070, or the
International Agreement and associated GQA administrative procedure.
c. While performing GQA on behalf of a foreign government, DCMA CMO QA FS must
perform the GQA responsibilities and process activities of the “Delegatee,” the appropriate
national authority of a supplying country performing GQA after acceptance of the RGQA. In
this role, the U.S. is considered the HN and DCMA the appropriate national authority.
d. Direct communication between DCMA QA FS and the QA FS of the foreign government
requesting GQA surveillance is highly encouraged. This communication can help clarify
ambiguous RGQA requirements and will foster a working relationship with our allies and
international customers. It assures the foreign government that their acquisitions are being
provided the expected visibility and GQA surveillance efforts that we expect when they perform
GQA on behalf of DCMA. Where a more formal communication is required, coordinate with
the DCMA country managers assigned to the DoDCCP.
e. Early coordination of requests by the foreign government with DCMA FS is encouraged
but must be followed up with a formal request for services through the DoDCCP. DCMA FS
must coordinate with the DoDCCP prior to providing any information requested by the foreign
government without having received a formal request for services through the Agency system of
record for RGQAs. DCMA CMO QA FS must provide the DoDCCP, via the Agency system of
record for RGQAs, the estimated hours expected to be expended in support of the international
delegation.
9.2. RESPONSE TO GOVERNMENT QUALITY ASSURANCE REQUEST.
a. RGQA and Contract Review. In addition to DCMA-MAN 2501-01, the RIAC, contract,
and all associated documentation received with the RGQA must be reviewed in accordance with
Sections 9 and 10 of AQAP-2070 to ensure DCMA CMO QA FS comply with the requirements
of the contract as related to the requested GQA. The results of the review must be used to assist
in planning the appropriate GQA activities. If clarifications are required, e-mail or telephone the
Delegator to obtain the necessary information to resolve issues.
b. Risk Review. DCMA FS must review the risks identified on the RIAC form and RGQA.
The risk information (risk statements, causes, ratings, etc.) must be compared to DCMA’s
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 9: Request For Contract Administrative Service Procedure – Government Quality
Assurance Performance DCMA Contract Management Office 37
current supplier risk assessment and, where additional risks are evident that would require GQA
surveillance, the RIAC must be updated and returned to the Delegator with the RGQAR. For
non-NATO nations not using the AQAP-2070 process, the RGQA must be updated and returned
to the Delegator.
(1) Where a DCMA risk assessment is not available, the risk information provided on the
RIAC and RGQA (risk statements, causes, ratings, etc.) will be compared to DCMA’s risk
impact indicators and supplier performance factors to determine if additional risks are present
and, if so, to update the RIAC or RGQA, as necessary.
(2) It is not necessary for the Delegator and Delegatee to agree on the risk identification
or assessment ratings; however, recommendations and comments will be provided to the
Delegator based on DCMA’s experience working with the supplier.
c. Delegation Acceptance Decision.
(1) Requests for GQA must normally be accepted by DCMA. DCMA CMO FS must
coordinate with the DoDCCP and the Delegator prior to rejecting the RGQA.
(2) DCMA CMO FS must accept, partially accept, or reject the request within 20
working days after acknowledgement by the DoDCCP. DCMA CMO QA FS must complete the
RGQAR form and, if necessary, update the risk information on the RIAC or RGQA form. The
completed forms must be uploaded into the Agency system of record for RGQAs and sent to the
DoDCCP. The DoDCCP must notify the customer of the Agency’s decision.
(3) Where a request for GQA can be only partially accepted, DCMA CMO FS must
contact the DoDCCP and explain the reasons for not fully accepting the request. An alternative
approach that might satisfy the intent of the original request must be provided in writing to the
Delegator using the RGQAR form. The DoDCCP must notify the Delegator.
(4) Performance on the partially-accepted portions of the delegation request must begin
immediately and must not be held up pending acknowledgement by the Delegator. Once
accepted, the GQA must not be terminated without the coordination and concurrence of the
Delegator.
(5) Notify the supplier that DCMA will be performing GQA surveillance on behalf of
the foreign government.
9.3. GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLANNING.
a. DCMA-MAN 2303-02 and Section 11 of AQAP-2070, must be used in determining the
GQA surveillance activities, methods, and techniques considered necessary to mitigate the
identified risks. Unless otherwise specified on the RGQA, the GQA activities identified in the
bulletized list must be planned and performed without the need for specific tasking in the
RGQA:
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 9: Request For Contract Administrative Service Procedure – Government Quality
Assurance Performance DCMA Contract Management Office 38
Documenting nonconformity and CARs to Suppliers
Providing risk status reports and copies of CARs to Delegator
Documenting results of GQA surveillance activities so they are traceable to RGQA
Analyzing GQA data and adjusting GQA surveillance plan and risk information
Consideration of subcontract delegations
Updating RIAC risk status/RGQA and reporting to Delegator
Reviewing supplier Quality Management System documentation as part of process
reviews
Verifying supplier’s investigations of customer complaints
Deviation permits and concessions authority (material review)
b. GQA surveillance plans must be used to plan, document, and execute the surveillance
necessary to satisfy the RGQA. The DCMA-planned GQA surveillance activities must be
traceable to the risks activities identified/requested on the RGQA, and if applicable, RIAC. It is
permissible for the DCMA CMO QA FS to use the GQA plan provided at Annex B of AQAP-
2070.
c. The planned GQA surveillance activities may be added to current DCMA surveillance
plans or a separate surveillance plan may be generated. In either case, traceability to the RGQA
must be maintained. Copies of DCMA surveillance plans must be provided to the Delegator
when requested.
9.4. PERFORM GOVERNMENT QUALITY ASSURANCE SURVEILLANCE.
a. GQA must be performed by the QAS in accordance with the applicable DCMA
Instructions/Manuals and Sections 12 and 13 of AQAP-2070.
b. During the course of GQA surveillance, certain GQA activities must be performed with or
without specific tasking on the RGQA. These support activities, identified in paragraph 9.3.a.,
must be performed in accordance with the applicable DCMA Instructions/Manuals unless
otherwise specified on the RGQA.
9.5. GOVERNMENT QUALITY ASSURANCE CLOSURE REPORT.
a. For AQAP-2070 based RGQAs, notification of completion is through a GQACR. DCMA
CMO QA FS must complete the GQACR and upload the completed form into the Agency
system of record for RGQAs. The form must be transmitted to the DoDCCP via the Agency
system of record for RGQAs within 15 working days of completion of the RGQA.
b. As part of the closure process, DCMA CMO QA FS must consider whether the status of
the risks, as stated on the current RIAC form, have increased, decreased, or remained stable as a
result of GQA surveillance. This information must be provided on the RIAC form or RGQA
form for non-NATO nations and uploaded into the Agency system of record for RGQAs.
Recommendations concerning future delegations will also be provided. The RIAC form(s) must
be transmitted to the DoDCCP via the Agency system of record for RGQAs with the RGQA as
noted in paragraph 9.5.a.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 9: Request For Contract Administrative Service Procedure – Government Quality
Assurance Performance DCMA Contract Management Office 39
c. Delegator/Delegatee satisfaction data and process improvement recommendations are
collected by means of the DFB form. DCMA CMO QA FS must submit a DFB form with the
closure report to receive feedback concerning the Delegator’s satisfaction with DCMA QA
services provided on their request. Where the Delegator has requested delegation feedback from
DCMA FS, the DFB form must be completed and transmitted to the DoDCCP via the Agency
system of record for RGQAs within 10 working days.
d. Copies of all DFB forms, either received from or sent to the other government’s QA
organization, must be provided via the Agency system of record for RGQAs to the DoDCCP
who must maintain record files for process improvement purposes.
e. Certificate of Conformity. It must be understood that the use of a Certificate of
Conformance in the DoD acquisition system has a very different result on GQA surveillance
activities than a Certificate of Conformity used within foreign governments’ procedures.
(1) Within the U.S. acquisition system the criteria for using a certificate of conformance
are found in Federal Acquisition Regulation (FAR) Part 46; FAR 46.504, “Certificate of
Conformance,” and must be authorized by contract, with the inclusion of FAR clause 52.246-15,
“Certificate of Conformance.” Once authorized in writing by the cognizant CMO, the certificate
is used “in lieu of source inspection” (GQA surveillance).
(2) Within most foreign governments, the Certificate of Conformity is required to be
submitted by the supplier on almost every shipment of every acquisition. The certificate is an
affirmation by the supplier, certifying that the products identified on the certificate conform in all
respects to the contract requirements. This form is used similar to a shipping document and, in
many countries payment to the supplier is not made until receipt of the Certificate of Conformity.
(3) When a Certificate of Conformity is a contractual requirement for the supplier and
when requested by the foreign government via the RGQA, DCMA CMO QA FS must sign the
Certificate of Conformity as an affirmation that GQA surveillance was performed in accordance
with the agreed to RGQA.
(4) AQAP-2070 includes an example of a Certificate of Conformity at Annex B. The
example shown is a two-part form. Part I is the Supplier Certificate of Conformity and Part II is
the GQAR’s Statement of GQA.
f. Records Retention. Records must be maintained in accordance with DCMA-MAN 4501-
04 and as required by the specific process Instructions. In addition, each DCMA CMO operating
under the purview of an International Agreement must establish and maintain files that include:
Active and completed RGQA forms
Active and completed RIAC forms
GQA Closure Reports
DFBs
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 9: Request For Contract Administrative Service Procedure – Government Quality
Assurance Performance DCMA Contract Management Office 40
GQA Surveillance Records for all activities performed on behalf of another government
GQA organization
9.6. CLOSURE OF REQUEST.
a. The DCMA CMO must close out the Agency system of record for RGQAs delegation and
complete the necessary GQACR, including updating the RIAC forms, and other forms used with
the request to indicate completion, then forward the forms via the Agency system of record for
RGQAs to the DoDCCP. An email to both the DoDCCP and the requestor may be sent with the
GQACR attached. This will ensure that both parties are aware of the requests completion.
b. Prior to closing the request, DCMA FS must accurately report all hours expended on
international delegations, on both fee-for-service work and no-cost work. The hours expended
must be reported in Defense Agencies Initiative (DAI) in whole hour increments using the
assigned document control number (DCN). This DAI information is used to recoup DCMA
costs associated with international delegations.
c. After all hours expended are reported and upon issuance of the GQACR and other
necessary forms, the DCMA CMO QA FS must close the RGQA by DCN. During the course of
the RGQA, all required forms must be completed and updated into the Agency system of record
for RGQAs for archiving by the DoDCCP.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 10: Export Controls 41
SECTION 10: EXPORT CONTROLS
10.1. INTERNATIONAL TRAFFIC IN ARMS REGULATIONS/EXPORT
ADMINISTRATION REGULATIONS OVERVIEW RELATED TO
INTERNATIONAL REQUESTS FOR CONTRACT ADMINISTRATION SERVICES.
a. The ITAR (Parts 120-130 of Title 22, CFR) is a set of U.S. Government regulations that
control the export and import of defense articles and services, including related technical data
identified on the United States Munitions List (USML). These regulations implement the
provisions of the Arms Export Control Act (AECA). The Department of State (DoS),
Directorate of Defense Trade Controls (DDTC), interprets and enforces the ITAR, including the
issuance of licenses and agreements. The goal of the ITAR is to safeguard U.S. national security
and further U.S. foreign policy objectives.
b. For practical purposes, ITAR regulations dictate that technical data, information, and
material pertaining to defense-related technologies (for items listed on the USML) may only be
shared with U.S. persons unless authorization from the DoS is received or a special exemption
applies. U.S. persons can face fines, imprisonment, or both, if they have, without proper
authorization or exemption, provided or allowed foreign persons access to ITAR controlled
defense articles, services, or technical data.
c. TheEARs (Parts 730-774 of Title 15, CFR) is a set of U.S. Government regulations that
control the export of dual-use items (items that have both commercial and military or
nonproliferation applications). The EAR implements the Export Administration Act (EAA).
d. The Department of Commerce (DoC), Bureau of Industry and Security (BIS), interprets
and enforces the EAR. Assignment of an Export Control Classification number on the
Commerce Control List (CCL) identifies many items subject to the EAR. Those items “subject
to the EAR” but not identified on the CCL are identified by the designator “EAR99.” The CCL
is part of the EAR in Supplement No. 1 to Part 774 of Title 15, CFR.
e. The DoD has entered into International Agreements with counterparts in foreign
governments for the reciprocal exchange of GQA and financial services. These agreements
allow DCMA to request GQA and/or financial services from the foreign government when
supplier performance is in the foreign country, in lieu of DCMA FS performing these services.
f. Occasionally, DCMAI CMOs administer contracts or subcontracts and receive requests for
financial services where ITAR restricts access to the supplies and associated technical data to
U.S. FS only. Most of these International Agreements do not adequately address these
restrictions and the required access authorizations. As a result, DCMAI CMO FS may only
request GQA or financial services from the foreign government by use of other methods of
authorization, such that the foreign government FS are allowed access to the defense articles,
services, and technical data when necessary in the performance of GQA on behalf of the U.S.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 10: Export Controls 42
g. Where ITAR restrictions are contractually imposed, the suppliers are obligated to protect
ITAR defense articles, services, and technical data from unauthorized export and also must
secure access authorization for foreign subcontractors.
h. The supplier’s responsibility for protection of ITAR specific items is found in the USML,
which designates categories of items that are defense articles or defense services. In many cases,
suppliers will subcontract the manufacture and/or assembly of items or parts of items identified
on the USML to subcontractors located in foreign countries. Subcontracting may involve the
export of technical data that is required for contract performance and/or product acceptance.
Prime suppliers must secure authorization for the export of defense articles and services.
Depending on the circumstances, the authorization could be in the form of:
• Temporary/Permanent Export Licenses (Form DSP-5, Form DSP-73, etc.)
MLAs
• TAAs
(1) All of the authorizations must identify the specific articles or services controlled; the
country where the defense articles, services or technical data will pass through or be used, the
companies or organizations authorized access; and the associated technical data.
(2) DFARS 252.225-7048, “Export-Controlled Items,” is a contract clause requiring the
contractor/supplier to comply with all applicable laws and regulations regarding export-
controlled items. The clause states that the supplier must flow down and include the substance
of this clause in all subcontracts.
(3) Pursuant to DFARS PGI 225.79, “Export-Control,” DCMA FS will not answer any
questions a supplier may ask regarding compliance with the ITAR or EAR, or questions
regarding the DoS requirement for suppliers to register in accordance with the ITAR. DCMA FS
must direct the supplier to paragraphs (b) and (c), respectively, of DFARS 252.225-7048, and
may inform the supplier to consult with the DoS or DoC. DCMA FS having questions regarding
the applicability of the EAR or ITAR to specific procurements or items, or interpretation of DoD
issuances regarding export controls, may contact the Defense Technology Security
Administration (DTSA) policy directorate by visiting their website.
i. Suppliers are responsible for compliance with ITAR and EAR restrictions. DCMA FS are
not responsible for performing oversight or surveillance of a supplier’s compliance with export
control requirements.
j. All DCMA FS have a responsibility to safeguard U.S. export-controlled items that they
may come in contact with during the performance of their official duties. DCMA FS are
reminded that export of ITAR-controlled defense articles, services, and technical data can occur
in the U.S. (a “deemed export”) as well as in foreign countries and may include covered defense
information (as defined in DFARS 204.73).
k. Foreign marked parts may sometimes pose a fraud indicator during product inspection and
acceptance. DCMA employees who suspect that an ITAR violation has occurred or a potential
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 10: Export Controls 43
ITAR violation has occurred, must immediately report the matter to the Contract Integrity Center
(CIC). Contact information for your local CIC Fraud Counsel is located on the Resource Page.
10.2. SAFEGUARDING CONTROLLED UNCLASSIFIED INFORMATION. Covered
defense information (as defined in DFARS PGI 204.73) is unclassified controlled technical
information or other information (as described in the Controlled Unclassified Information (CUI)
Registry) that requires safeguarding or dissemination controls pursuant to and consistent with
law, regulations, and government wide policies. See DCMA-MAN 3301-08, “Information
Security,” for information regarding safeguarding CUI.
10.3. INTERNATIONAL TRAFFIC IN ARMS REGULATIONS - RELATED REQUEST
PROCEDURE - DCMA CONTRACT MANAGEMENT OFFICE.
a. The importance of the CRR process cannot be over emphasized considering its impact to
the International Request for CAS process. The DCMA CRR must include a determination as to
the applicability of ITAR restrictions or other export controls to the contract or
subcontract/purchase order being reviewed.
b. The inclusion of DFARS clause 252.225-7048 is required for all contracts and does not
imply that ITAR or EAR restrictions exist.
c. DFARS 252.225-7047, “Exports by Approved Community Members in Performance of
the Contract. There are Defense Trade Cooperation (DTC) Treaties that permit the export of
certain U.S. defense articles, technical data, and defense services without U.S. export licenses or
other written authorization under the ITAR, into and within the Approved Community, as long as
the exports are in support of purposes specified in the DTC Treaties. If this clause is cited in the
contract, DCMA CMO QA FS must review DFARS 252.225-7047 and DFARS 225.79, “Export
Control” in its entirety to determine its applicability to the contract/subcontract. Specific defense
articles that are not U.S. DoD Treaty-eligible will be identified as such in those contract line
items that are otherwise U.S. DoD Treaty-eligible. (See Glossary for definitions of DTC and
Approved Community.)
d. The CRR must include a review of the applicable export license, MLA, or TAA. Some
contracts contain export-control language without referencing a specific DFARS clause.
Examples of ITAR restrictions identified on contract/subcontract are:
(1) Inclusion of a military service specific clause, such as the Air Force Material
Command (AFMC) FAR Supplement 5352.227.9000, “Export-Controlled Data Restrictions
(AFMC).”
(2) Inclusion of specific export-control language or ITAR restrictions, such as technical
data provided to the seller in support of the contract where the seller’s performance of the
contract is authorized by the applicable U.S. State Department authorization number.
e. Coordination with the Supplier. The CMO will discuss the contractual ITAR restrictions
with the supplier and the applicability of ITAR to subcontractors both in the U.S. and OCONUS.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 10: Export Controls 44
It is highly recommended that a process be established for identifying subcontractors and
subcontracts whose defense articles, services, or technical data is protected by export controls.
(1) The process must include a listing of contracts and associated subcontracts imposing
ITAR restrictions, with reference to the export license, MLA, or TAA.
(2) Export license restrictions, access authorizations, and agreements must be flowed
down to the applicable subcontractors through the applicable subcontracts. Also, as stated in
paragraph (e) of DFARS 252.225-7048, “The Contractor must include the substance of this
clause, including this paragraph (e), in all subcontracts.”
f. DCMA CMO QA FS must determine if GQA is required at the foreign supplier’s location
based on the risk assessment and the GQA determination made in Section 3.
g. If GQA surveillance or financial services are to be delegated to a DCMAI CMO, copies of
all applicable sections of export licenses, MLA, or TAA relative to the subcontract/purchase
order must be provided with the delegation, if available. As a minimum, the referenced DFARS
clauses or the contract page numbers that contain the ITAR language, license and agreement
numbers, expiration dates, and other relevant information must be provided on the delegation.
h. The delegation must be coordinated with the DCMAI CMO cognizant of the
subcontractor in advance of the delegation for coordination purposes and to determine whether
assistance is required to obtain access for HN QA FS to the export-controlled items.
i. The DCMA CMO will work with the supplier (DoS export license holder) to amend or
modify the export license, access authorizations, or agreements, or to obtain a sub-license. If
necessary, the CMO may contact the Procurement Contracting Officer (PCO) to solicit an ITAR
exemption through the appropriate military channels in order to obtain export-controlled access
for the HN during the performance of the GQA. The decision to amend a license, agreement, or
to pursue an exemption rests with the supplier and will depend on the circumstances associated
with the export controls. Consult with the DCMAI Functional Director.
j. As part of their GQA Surveillance Planning effort, DCMA CMO QA FS must schedule
and perform process reviews of the supplier’s processes for flowing contract requirements to
their subcontractors.
10.4. INTERNATIONAL TRAFFIC IN ARMS REGULATIONS - RELATED REQUEST
PROCEDURE - DCMAI CONTRACT MANAGEMENT OFFICE.
a. CRR must include a determination concerning the applicability of ITAR restrictions or
other export controls to the contract or subcontract/purchase order subject to review.
b. The CRR must include a review of the applicable export license, MLA, or TAA to
identify specific defense article or defense service restrictions, technical data, and information
restrictions, and access authorizations. If this information is not available with the contract,
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 10: Export Controls 45
subcontract, or delegation, the DCMAI FS must contact the Delegator and request the
information.
(1) DCMAI FS must not proceed with requesting GQA or financial services from the
HN until the information is reviewed and clearly understood.
(2) All restrictions and authorizations must be documented in the surveillance plan or
must be clearly traceable from the surveillance plan.
c. The inclusion of DFARS 252.225-7048 is required for all contracts and does not imply
ITAR restrictions apply.
d. DFARS 252.225-7047. There are DTC Treaties that permit the export of certain U.S.
defense articles, technical data, and defense services, without U.S. export licenses or other
written authorization under the ITAR, into and within the Approved Community, as long as the
exports are in support of purposes specified in the DTC Treaties. If this clause is cited in the
contract, DCMAI CMO QA FS must review DFARS 252.225-7047 and DFARS Subpart 225.79
in their entirety to determine their applicability to the contract/subcontract. Specific defense
articles that are not U.S. DoD Treaty-eligible will be identified as such in those contract line
items that are otherwise U.S. DoD Treaty-eligible. (See Glossary for definitions of DTC and
Approved Community.)
e. Some contracts contain export-control language without referencing a specific DFARS
clause. Examples of ITAR restrictions identified on contract/subcontract are:
(1) Inclusion of a military service specific clause, such as AFMC FAR Supplement
5352.227.9000.
(2) Inclusion of specific export-control language or ITAR restrictions, such as technical
data provided to the seller in support of this contract and seller’s performance of this contract is
authorized by the applicable DoS authorization number.
f. HN Access Authorization. DCMAI CMO QA FS must determine if the GQA or financial
services will be requested from the HN FS. If exceptions apply, as discussed in Section 4,
paragraph 4.2.d., DCMAI FS must plan and perform the required activities.
g. DCMAI FS must determine whether the HN FS are authorized access to the ITAR export-
controlled defense articles or technical data. Methods of access authorization include:
(1) International Agreements. The method of granting access to HN FS is through the
security arrangement clauses of the individual International Agreements. This provides an
umbrella-type access authorization for ITAR or CUI. As new agreements arise or current
agreements are modified, this type access authorization may be included in the agreement.
(2) Exchange of Letters (EoL). Where the security provisions of a current International
Agreement do not contain the access authorization to ITAR or CUI, the agreements must be
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 10: Export Controls 46
clarified through an EoL. The EoL is an administrative procedure that outlines the required
aspects for access and protection requirements for U.S. origin export-controlled information.
The EoL must be agreed to by both governments prior to any access to U.S. origin export-
controlled information by the foreign government. Questions concerning process initiation,
coordination, and approval must be directed to the DCMAI Functional Director.
(3) Amendment of Export License, MLA, or TAA. DCMAI FS must contact the PCO or
the DCMA CMO Delegator and request the license or agreements be revised to provide access to
HN FS. See the information at paragraph 9.3.g.
(4) No portion of GQA surveillance or financial services will be requested or performed
by HN FS until access is authorized. If implementation of GQA surveillance or financial
services is time sensitive, the surveillance or services must be planned and executed by DCMAI
FS.
h. Request Preparation. After all the applicable export-controlled information is received,
including the access authorization for the HN FS, the request can be coordinated with the HN
and the RGQA, RIAC, or financial service request can be completed. Early coordination is
permissible, however, HN FS are not authorized to act on behalf of the DoD/DCMA until access
authorization is received and the request is accepted by the HN.
i. RGQA or Request for Government Contract Audit Services (RGCAS) forms modified for
ITAR requirements must be used to request GQA surveillance or financial services (see
Resource Page for template forms). The RGQA, RGQAR and the RGCAS forms have been
modified for ITAR requests. A request “valid to” date has been included in the form so that
unless the RGQA or RGCAS is revised, the delegation will expire on that date and all support
from the HN will cease regardless of the estimated contract final delivery date. This will assist
in providing a more active role in managing the delegation and a higher degree of organizational
management visibility.
j. Specific export-controlled defense articles, services, and technical data must be identified
on the ITAR RGQA within the product description ITAR Exemption Tracking No. 09-19. The
ITAR RGQA/RGCAS must be signed by the Requestor’s Team Leader and reviewed by the
HNC, if one is assigned to the DCMAI CMO. The RGQA/RGCAS must be forwarded to the
HN’s focal point.
k. Copies of the export license, MLAs, or TAAs must not be provided to the HN
organization to prevent proprietary information disclosure. The supplier must be notified that the
contract is being delegated to the HN GQA/Financial services organization.
l. Visibility. Each DCMAI CMO requesting GQA Surveillance or financial services of
ITAR-controlled defense articles and technical data must develop a process for managing and
tracking ITAR delegations and providing the appropriate level of management visibility.
m. RGQA/RGCAS Closure.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Section 10: Export Controls 47
(1) A request “valid to” date has been included on the ITAR modified RGQA/RGCAS
form so that unless the RGQA/RGCAS is revised, the delegation will expire on that date and all
support from the HN will cease regardless of the estimated contract final delivery date.
(2) The DCMAI CMO must forward a letter notifying the supplier that the request to the
HN has been terminated and they must not be provided access to ITAR-restricted defense articles
and technical data/information.
(3) If GQACR and RIAC, RGQA or financial services reports have not been received,
contact the HN focal point and remind them of the AQAP-2070 or the International
Agreement/GQA administrative procedure requirement for requested forms. On the second
attempt for the information, process the request to the HN’s CCP and include a DFB, as
applicable.
(4) Upon receipt of the GQACR or other notification of GQA or financial services
completion, DCMAI CMO QA FS must close the RGQA/RGCAS in the system they use for
tracking and managing RGQAs to the HN.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Glossary - Definitions 48
GLOSSARY
G.1. DEFINITIONS.
Agency System of Record. The Agency system of record is the authoritative data source for a
given data element or piece of information.
Approved Community. U.S. Government, U.S. entities that are registered and eligible
exporters, and certain government and industry facilities in Australia or the United Kingdom that
are approved and listed by the U.S. Government. Community lists are accessible on the Manual
Resource Page.
Concession (See Deviation Permit). Permission to use or release a product that does not
conform to specified contract requirements. NOTE: A concession is generally limited to the
delivery of a product that has nonconforming characteristics within specified limits for an agreed
time or quantity of that product. (Source: ISO 9000)
DCMA CMOs. As used in this Manual, refers to CMOs located in the U.S. (CONUS).
DCMAI CMOs. As used in this Manual, refers to CMOs located outside of the U.S. (OCONUS).
DTC Treaty (1) The Treaty Between the Government of the United States of America and the
government of the United Kingdom of Great Britain and Northern Ireland concerning Defense
Trade Cooperation signed at Washington and London on June 21 and 26, 2007; or (2) The
Treaty Between the Government of the United States of America and the Government of
Australia Concerning Defense Trade Cooperation, signed at Sydney on September 5, 2007.
Delegatee. The appropriate national authority of a supplying nation performing GQA after
acceptance of the RGQA. When performing GQA for a foreign government, the U.S. is
considered the HN and DCMA the appropriate national authority.
Delegator. The appropriate authority of a purchasing nation requesting GQA in a supplying
nation.
Deviation Permit (See Concession). Permission to depart from the originally specified contract
requirements of a product prior to realization. NOTE: A deviation permit is generally given for
a limited quantity of product or period of time, and for a specific use. (Source: ISO 9000)
DoDCCP. When a foreign government or international organization submits a contract
administration service request involving a direct commercial sales contract, it will be sent to the
DoDCCP.
EAR. The EARs (EAR; Parts 730-774 of Title 15, CFR) is a set of U.S. Government regulations
that control the export of dual-use items (items that have both commercial and military or
nonproliferation applications). The EAR implements the EAA.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Glossary - Definitions 49
Host Nation. The nation that performs the GQA or financial services in their nation on behalf of
another nation or NATO organization. When DCMA performs the GQA or financial services in
this capacity, the U.S. is the HN.
International Agreement. Any agreement concluded with one or more foreign governments
(including their agencies or organizations) or with an international organization that;
Is signed or agreed to by appropriate-level FS of the DoD
Signifies the intention of the parties to be bound in international law
Can be in the form of an International Agreement, MOU, memorandum of
agreement, memorandum of arrangements, technical arrangement, cooperative
agreement, or any other name
ITAR. Set of U.S. Government regulations that control the export and import of defense
articles and services including related technical data identified on the USML (Part 121 of Title
22, CFR). These regulations implement the provisions of the AECA, and are described in 22
Parts 120-130 of Title 22, CFR.
OCONUS. Refers to all other areas not included in the definition for U.S.
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Glossary - Acronyms 50
GLOSSARY
G.2. ACRONYMS.
ABCAS Acquisitions Branch Contract Assurance Standards
AECA Arms Export Control Act
AFMC Air Force Material Command
ALRE Air Launch and Recovery Equipment
AQAP Allied Quality Assurance Publication
CAA Canadian Audit Authority
CAR Corrective Action Request
CAS Contract Administration Service
CCL Commerce Control List
CCP Central Control Point
CFR Code of Federal Regulations
CIC Contract Integrity Center
CMO Contract Management Office
CONUS Continental United States
CSI Critical Safety Items
CRR Contract Receipt and Review
CUI Controlled Unclassified Information
DAI Defense Agencies Iniative
DCA Data Collection and Analysis
DCAA Defense Contract Audit Agency
DCMA-FBR DCMA HQ International and Federal Business Division
DCMAI DCMA International
DCMA-INST DCMA Instruction
DCMA-MAN DCMA Manual
DCMAF DCMA Form
DCN Document Control Number
DDTC Director, Defense Trade Controls
DFARS Defense Federal Acquisition Regulation Supplement
DFARS PGI Defense Federal Acquisition Regulation Supplement Procedures,
Guidance, and Information
DFB Delegation feedback
DoC Department of Commerce
DoDCCP Department of Defense Central Control Point
DoDD DoD Directive
DoS Department of State
DPC Defense Pricing and Contracting
DTC Defense Trade Cooperation
EAA Export Administration Act
ECARS Electronic Contract Administration Request System
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Glossary - Acronyms 51
ECD estimated completion date
EoL Exchange of Letters
EAR Export Administration Regulation
FAR Federal Acquisition Regulation
FLS First Level Supervisor
FMS Foreign Military Sales
GAGAS Generally Accepted Governement Audit Standards
GCQA Government Contract Quality Assurance
GQA Government Quality Assurance
GQACR Government Quality Assurance Closure Report
GQAR Government Quality Assurance Representative
HN Host Nation
HNC Host Nation Coordinator
HQ Headquarters
ICSM International Contract Service Manager
ITAR International Traffic in Arms Regulation
MLA Manufacturing License Agreement
MOU Memorandum of Understanding
NASA National Aeronautics and Space Administration
NATO North Atlantic Treaty Organization
OCONUS outside continental United States
PCO Procurement Contracting Office
PGI Procedures, Guidance, and Information
QA Quality Assurance
QALI Quality Assurance Letter of Instruction
RDP Reciprocal Defense Procurement
RGCAS Request for Government Contract Audit Services
RGQA Request for Government Quality Assurance
RGQAR Response to Government Quality Assurance Request
RIAC Risk Identification, Assessment and Communication
RPP Risk Profile and Plan
STANAG Standardization Agreement
TAA Technical Assistance Agreement
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
Glossary - Acronyms 52
USC United States Code
USML United States Munitions List
DCMA-MAN 2501-11, March 4, 2019
Change 1, Effective September 25, 2019
References 53
REFERENCES
Code of Federal Regulation, Title 15
Code of Federal Regulation, Title 22
Air Force Material Command (AFMC), Federal Acquisition Regulation (FAR) Supplement
5352.227.9000, “Export-Controlled Data Restrictions,” July 1997
Allied Quality Assurance Publication (AQAP) - 2070, “NATO Mutual Government Quality
Assurance Process”
DFARS 225.870, “Contracting with Canadian Contractors,” as amended
DFARS clause 252.225-7048, “Export-Controlled Items,” June 2013
DFARS clause 252.225-7047, “Exports by Approved Community Members in Performance of
the Contract”
DFARS PGI 242.002, “Interagency Agreements,” November 9, 2005
DFARS Subpart 225.79, “Export Control,” June 26, 2013
DCMA-INST 309, “Government Contract Quality Assurance (GCQA) Surveillance Planning,”
February 2012
DCMA-INST 1201, “Corrective Action Process,” December 4, 2012
DCMA-INST 2101, “Product Acceptance and Proper Payment,” February 14, 2019
DCMA-INST 2501, “Contract Maintenance,” August 15, 2017
DCMA-MAN 2101-04 “Delegate Surveillance,” August 1, 2018
DCMA-MAN 2301-06, “Discrepancy Processing,” TBD
DCMA-MAN 2303-01, “Surveillance Assess Risk,TBD
DCMA-MAN 2303-02, “Surveillance Plan Events,TBD
DCMA-MAN 2303-04, “Surveillance – Document Results, Corrective Actions and Provide
Feedback, TBD
DCMA-MAN 2401-01, “Negotiation Intelligence Procedures,” January 3, 2019
DCMA-MAN 2501-01, “Contract Receipt and Review,” TBD
DCMA-MAN 3301-08, “Information Security,” January 21, 2019
DCMA-MAN 4301-04, “Accounting,” TBD
DCMA-MAN 4501-04, “Records Management,” TBD
DoD Directive 5105.64, “Defense Contract Management Agency (DCMA),” January 10, 2013
DoD Directive 5530.3, “International Agreements,” November 21, 2003
FAR Part 46, “Quality Assurance,” March 2, 2015
FAR 46.504, “Certificate of Conformance,” June 14, 2007
FAR clause 52.246-15, “Certificate of Conformance,” April 1984
NATO Standardization Agreement (STANAG) 4107, “Mutual Acceptance of Government
Quality Assurance and Usage of the Allied Quality Assurance Publications (AQAP),
December 18, 2017